The company building the Trans Mountain pipeline expansion is warning the project’s completion could be delayed by two years if the Canada Energy Regulator does not allow a previously rejected request for a pipeline variance.
In a regulatory filing last Thursday, Trans Mountain Corporation said such a delay would be “catastrophic” for the pipeline project, which is currently more than 97% complete, The Canadian Press reports. It said a delay of that length would result in billions of dollars of losses for the company, which is a Crown corporation.
“These outcomes would not be in the public interest,” the filing states.
The development is just the latest in a series of hurdles Trans Mountain has faced as it races against the clock to finish its massive, and massively over-budget, pipeline construction project.
The Trans Mountain pipeline is Canada’s only oil pipeline to the west coast, and its expansion will boost the pipeline’s capacity to 890,000 barrels per day from 300,000 bpd currently.
The project’s completion, which had been expected in early 2024, is eagerly awaited by this country’s fossil industry, which expects to benefit from improved access to export markets.
The pipeline expansion is also expected to reduce the Western Canada Select differential, which is a term for the discount Canadian oil companies typically apply to their product, in part due to lack of export capacity.
But the pipeline project has run into construction difficulties in its home stretch. Trans Mountain Corporation has already had to alter the route slightly near Kamloops, British Columbia due to difficulty drilling a tunnel.
The newest challenges are related to hard rock conditions. In October, the Crown corporation asked the regulator to allow it to use a different diameter, wall thickness, and coating for a 2.3-kilometre stretch of pipeline to make construction easier, but the regulator denied that request earlier this month.
Now, Trans Mountain says it has reason to believe that proceeding with the current construction plan through complex hard rock conditions could compromise a borehole and result in the failure of drilling equipment.
It is once again requesting that it be allowed to alter the type of pipe used, saying the risks of continuing are “more serious and acute than previously understood.”
In an email Friday, Canada Energy Regulator spokeswoman Ruth Anne Beck said a decision-making process and timeline for Trans Mountain’s latest request is still being determined.
Trans Mountain has asked the regulator to make a decision before January 9 in order to prevent unnecessary delays.
The federal government made Canadians the involuntary owners of the Trans Mountain pipeline in 2018 following an extraordinary ultimatum from previous owner Kinder Morgan Canada.
The project’s costs have spiralled through the course of construction from an original estimate of C$5.4 billion to the most recent estimate of $30.9 billion.
Trans Mountain Corporation has said that if the pipeline doesn’t begin shipping oil in early 2024 as expected, it will incur lost revenues to the tune of about $200 million for each month of delay.
One observer pointed out that those numbers suggest revenue of just $2.4 billion per year on a project that will cost at least $30.9 billion to complete.
This report by The Canadian Press was first published December 15, 2023.














This is priceless! The company bought by the government tells the government there’s going to be a bit of a delay ‘cus their well paid engineers misjudged how difficult it was to drill through rock (hard rock at that, who would-a-thought?). What next in this ongoing saga of mismanagement?
As one of those “involuntary owners,” I say “scrap the whole project.” (or no, use the pipeline to pump water to drought stricken Alberta in a save face gesture of good will).
$2.4 billion a year. Hmmm, less 30.9B, that’s 12.875 years, puts us at about 2037 when we break even, assuming no hidden costs or cost overruns (ha ha ha) and if we don’t give up fossil fuels by 2050, nothing’s going to matter anyway. That gives us about 13 years to make a some money, oh but wait, the Government wants to sell the TMX. Who on Earth would be fool enough to buy such a stranded pink elephant? Not the fossil fuel industry, not when they can get the people of Canada to pay for it.
Well done Government of Canada.