The Energy Mix
Subscribe
Donate
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
    • Climate Glossary
    • What If We Changed the Conversation on Climate Change?
    • Eco-Anxiety
  • About
  • Contact
No Result
View All Result
The Energy Mix
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
    • Climate Glossary
    • What If We Changed the Conversation on Climate Change?
    • Eco-Anxiety
  • About
  • Contact
Subscribe
Donate
The Energy Mix
Subscribe

Trans Mountain Route Change Amounts to ‘Cultural Genocide’: Secwepemc Knowledge Keeper

October 9, 2023
Reading time: 6 minutes
Full Story: The Canadian Press with files from The Energy Mix
Author: Alessia Passafiume

CTV News/Twitter

CTV News/Twitter

The latest route change for the controversial Trans Mountain pipeline would threaten a sacred site—Pipsell, or Jacko Lake, near Kamloops, BC—and amount to a continuation of cultural genocide, a Secwepemc knowledge keeper says.

A Secwepemc law called X7ensq’t says that if you disrespect the land and don’t take care of it properly, the land and the sky will turn on you, The Canadian Press reports.

“It’s a serious law,”’ knowledge keeper Mike McKenzie told CP. He said he wonders “how much farther” people want to go in violating it.

Pipeline construction at Pipsell [pdf] resumed last week after the Canada Energy Regulator approved a change to the Trans Mountain route.

“Without that place, we lose a big part of ourselves,” said McKenzie, who noted the Secwepemc creation story takes place in Pipsell, and their laws and customs are born from that land.

“This is our Vatican. This is our Notre Dame. This is a place that gives our people an identity and kept our people grounded since time immemorial.”

The CER approved Trans Mountain’s application to modify the pipeline’s route in late September, a decision that could spare the government-owned pipeline project another nine-month delay. The regulator made the ruling just one week after hearing oral arguments from Trans Mountain and Stk’emlupsemc te Secwepemc Nation, which opposed the route change.

The Nation said the corridor near Jacko Lake holds “profound spiritual and cultural significance,” and while it supported the project overall, it opposed the deviation application.

The Nation said it only consented to construction in the first place under the understanding that the company would minimize surface disturbances.

Get the latest climate news and analysis, direct to your inbox.

Subscribe Today

View our latest digests

‘Irreparable Harm’ to ‘Cultural Keystone’

A written response that Stk’emlupsemc te Secwepemc Nation provided to the regulator said a change in construction methodology would cause “significant and irreparable harm” to its culture.

It added that it did not provide free, prior and informed consent for the route deviation, as prescribed under the United Nations Declaration on the Rights of Indigenous Peoples.

It had told the federal regulator in 2018, when the Trans Mountain expansion project was still in the approval process, that Pipsell is a “cultural keystone place and sacred site.”

Trans Mountain said the route change was required because it ran into engineering difficulties in the area related to the construction of a tunnel. The regulator ultimately decided the pipeline’s route could deviate from what was originally planned for a 1.3-kilometre stretch of pipe, and the company could change its construction method for that section.

The company confirmed Wednesday that it has resumed work at the Pipsell site. It said in a statement that it recognizes the area is of “sacred importance” and it is “committed to remaining respectful of the spiritual and cultural significance of this land.”

“All care will be taken to ensure existing archeological and traditional land use sites are completely avoided and not touched by this construction,” the statement went on.

“We greatly value our partnership with the (Stk’emlupsemc te Secwepemc) and will continue to invite representatives to walk the site and share contingency and mitigation plans.”

The company said it is committed to “meaningful engagement and effective relationships” with Indigenous communities along the pipeline corridor, and noted 69 agreements are in place with communities along the right-of-way, including the Stk’emlupsemc te Secwepemc.

Still, McKenzie, often speaking through tears, said he was devastated to hear the news that construction had resumed.

This is the Face of Reconciliation?

McKenzie said the project flies in the face of reconciliation, and Canada’s reputation as a “model site” for what better relationships could look like.

“We showed the world that we can reconcile and we can do work together based on something good,” said McKenzie.

But he said the recent decision, and the fact the community did not provide consent, goes against that.

“The fact that they’re going to desecrate a sacred site, after all the work that we’ve done, tells me that they’re not serious about reconciliation at all.”

In an interview Friday, federal Crown-Indigenous Relations Minister Gary Anandasangaree said he doesn’t “want to pass the buck,” but said the decision was not in his purview. He noted government departments and agencies are required to follow the United Nations Declaration on the Rights of Indigenous Peoples. Trans Mountain has operated as a federal Crown corporation ever since the federal government bought taxpayers a pipeline in 2018.

“I certainly can say that as a federal government, we’re very much committed to ongoing consultation,” Anandasangaree said.’

It’s not the first time Pipsell has been proposed as a development site, CP writes. In 2017, Stk’emlupsemc te Secwepemc Nation stated it did not give its free, prior and informed consent for the Ajax Mine Project to be developed in the area.

“The oral histories associated with Pipsell are foundationally connected to our Secwepemc laws that deal with the reciprocal and mutually accountable relationships between humans and the environment,” reads a March 2017 document the Nation submitted as part of the approval process for the Ajax project.

“We assert the right to maintain and exercise our traditional and contemporary cultural practices, and carry on our customs and spiritual activities in the distinct locations marked by our Ancestors.”

The federal government ultimately decided not to approve the project.

McKenzie said the site continues to hold significant meaning for his community—and for him personally, since it was where he did his vision quest. But given that the hearing for the Trans Mountain route change decision was held in Calgary, he added, it was hard for individual community members to express just how important the site is, as they would have had to travel more than 700 kilometres to attend.

The federal government bought the Trans Mountain pipeline for $4.5 billion in 2018, after previous owner Kinder Morgan Canada Inc. threatened to scrap the planned expansion project in the face of Indigenous and environmental opposition and regulatory hurdles. It has already been plagued by construction-related challenges and delays, CP notes.

And the pipeline’s price tag has since spiralled (as big infrastructure projects are wont to do): first to $12.6 billion, then to $21.4 billion, and most recently to $30.9 billion, the capital cost estimate as of March, prompting critics to label the “out-of-control” infrastructure project a “catastrophic boondoggle”.

“If that isn’t the land and the sky turning on this company, I don’t know what is,” said McKenzie.

The main body of this story was first published by The Canadian Press on October 8, 2023.







in Canada, Indigenous Rights & Reconciliation, Oil Sands, Pipelines / Rail Transport, Society & Culture

Trending Stories

(Julie Dabrusin/Facebook)
Carbon Pricing

EXCLUSIVE: Carbon Tax Exemption for Canada Would Break World Trade Rules, EU Law

November 3, 2026
1.6k
Alberta Environment and Protected Areas Minister Grant Hunter, Alberta Newsroom/flickr
Legal & Regulatory

Alberta Accused of Rushing Environmental Law Changes Behind Closed Doors

November 5, 2026
693
Finance Minister François-Philippe Champagne at 2025 Collision Conferencef/flickr
Finance & Investment

Federal Budget Funds Clean Grid and Energy Efficiency, Touts ‘Investment Supercycle’ Built on Major Projects

November 6, 2026
684

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

I agree to the Terms & Conditions and Privacy Policy.

Get the latest climate news and analysis, direct to your inbox.

Subscribe Today

Related Articles

Pimicikamak Faces Long Road to Repair After Havoc-Wreaking Power Outage

Pimicikamak Faces Long Road to Repair After Havoc-Wreaking Power Outage

February 4, 2026
First Nations Chiefs Call out Ottawa Over Pipeline Deal That Doesn’t Mention Water

First Nations Chiefs Call out Ottawa Over Pipeline Deal That Doesn’t Mention Water

January 26, 2026
SaskPower Signs Power Purchase Deal with 50% Indigenous-Owned Solar Farm

SaskPower Signs Power Purchase Deal with 50% Indigenous-Owned Solar Farm

January 19, 2026

Actions Speak Louder Than Words

by Mitchell Beer
November 2, 2026

…

Follow Us

Trans Mountain Route Change Amounts to ‘Cultural Genocide’: Secwepemc Knowledge Keeper

October 9, 2023
Reading time: 6 minutes
Full Story: The Canadian Press with files from The Energy Mix
Author: Alessia Passafiume

CTV News/Twitter

CTV News/Twitter

The latest route change for the controversial Trans Mountain pipeline would threaten a sacred site—Pipsell, or Jacko Lake, near Kamloops, BC—and amount to a continuation of cultural genocide, a Secwepemc knowledge keeper says.

A Secwepemc law called X7ensq’t says that if you disrespect the land and don’t take care of it properly, the land and the sky will turn on you, The Canadian Press reports.

“It’s a serious law,”’ knowledge keeper Mike McKenzie told CP. He said he wonders “how much farther” people want to go in violating it.

Pipeline construction at Pipsell [pdf] resumed last week after the Canada Energy Regulator approved a change to the Trans Mountain route.

“Without that place, we lose a big part of ourselves,” said McKenzie, who noted the Secwepemc creation story takes place in Pipsell, and their laws and customs are born from that land.

“This is our Vatican. This is our Notre Dame. This is a place that gives our people an identity and kept our people grounded since time immemorial.”

The CER approved Trans Mountain’s application to modify the pipeline’s route in late September, a decision that could spare the government-owned pipeline project another nine-month delay. The regulator made the ruling just one week after hearing oral arguments from Trans Mountain and Stk’emlupsemc te Secwepemc Nation, which opposed the route change.

The Nation said the corridor near Jacko Lake holds “profound spiritual and cultural significance,” and while it supported the project overall, it opposed the deviation application.

The Nation said it only consented to construction in the first place under the understanding that the company would minimize surface disturbances.

Get the latest climate news and analysis, direct to your inbox.

Subscribe Today

View our latest digests

‘Irreparable Harm’ to ‘Cultural Keystone’

A written response that Stk’emlupsemc te Secwepemc Nation provided to the regulator said a change in construction methodology would cause “significant and irreparable harm” to its culture.

It added that it did not provide free, prior and informed consent for the route deviation, as prescribed under the United Nations Declaration on the Rights of Indigenous Peoples.

It had told the federal regulator in 2018, when the Trans Mountain expansion project was still in the approval process, that Pipsell is a “cultural keystone place and sacred site.”

Trans Mountain said the route change was required because it ran into engineering difficulties in the area related to the construction of a tunnel. The regulator ultimately decided the pipeline’s route could deviate from what was originally planned for a 1.3-kilometre stretch of pipe, and the company could change its construction method for that section.

The company confirmed Wednesday that it has resumed work at the Pipsell site. It said in a statement that it recognizes the area is of “sacred importance” and it is “committed to remaining respectful of the spiritual and cultural significance of this land.”

“All care will be taken to ensure existing archeological and traditional land use sites are completely avoided and not touched by this construction,” the statement went on.

“We greatly value our partnership with the (Stk’emlupsemc te Secwepemc) and will continue to invite representatives to walk the site and share contingency and mitigation plans.”

The company said it is committed to “meaningful engagement and effective relationships” with Indigenous communities along the pipeline corridor, and noted 69 agreements are in place with communities along the right-of-way, including the Stk’emlupsemc te Secwepemc.

Still, McKenzie, often speaking through tears, said he was devastated to hear the news that construction had resumed.

This is the Face of Reconciliation?

McKenzie said the project flies in the face of reconciliation, and Canada’s reputation as a “model site” for what better relationships could look like.

“We showed the world that we can reconcile and we can do work together based on something good,” said McKenzie.

But he said the recent decision, and the fact the community did not provide consent, goes against that.

“The fact that they’re going to desecrate a sacred site, after all the work that we’ve done, tells me that they’re not serious about reconciliation at all.”

In an interview Friday, federal Crown-Indigenous Relations Minister Gary Anandasangaree said he doesn’t “want to pass the buck,” but said the decision was not in his purview. He noted government departments and agencies are required to follow the United Nations Declaration on the Rights of Indigenous Peoples. Trans Mountain has operated as a federal Crown corporation ever since the federal government bought taxpayers a pipeline in 2018.

“I certainly can say that as a federal government, we’re very much committed to ongoing consultation,” Anandasangaree said.’

It’s not the first time Pipsell has been proposed as a development site, CP writes. In 2017, Stk’emlupsemc te Secwepemc Nation stated it did not give its free, prior and informed consent for the Ajax Mine Project to be developed in the area.

“The oral histories associated with Pipsell are foundationally connected to our Secwepemc laws that deal with the reciprocal and mutually accountable relationships between humans and the environment,” reads a March 2017 document the Nation submitted as part of the approval process for the Ajax project.

“We assert the right to maintain and exercise our traditional and contemporary cultural practices, and carry on our customs and spiritual activities in the distinct locations marked by our Ancestors.”

The federal government ultimately decided not to approve the project.

McKenzie said the site continues to hold significant meaning for his community—and for him personally, since it was where he did his vision quest. But given that the hearing for the Trans Mountain route change decision was held in Calgary, he added, it was hard for individual community members to express just how important the site is, as they would have had to travel more than 700 kilometres to attend.

The federal government bought the Trans Mountain pipeline for $4.5 billion in 2018, after previous owner Kinder Morgan Canada Inc. threatened to scrap the planned expansion project in the face of Indigenous and environmental opposition and regulatory hurdles. It has already been plagued by construction-related challenges and delays, CP notes.

And the pipeline’s price tag has since spiralled (as big infrastructure projects are wont to do): first to $12.6 billion, then to $21.4 billion, and most recently to $30.9 billion, the capital cost estimate as of March, prompting critics to label the “out-of-control” infrastructure project a “catastrophic boondoggle”.

“If that isn’t the land and the sky turning on this company, I don’t know what is,” said McKenzie.

The main body of this story was first published by The Canadian Press on October 8, 2023.







in Canada, Indigenous Rights & Reconciliation, Oil Sands, Pipelines / Rail Transport, Society & Culture

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

I agree to the Terms & Conditions and Privacy Policy.

Related Articles

Pimicikamak Faces Long Road to Repair After Havoc-Wreaking Power Outage

Pimicikamak Faces Long Road to Repair After Havoc-Wreaking Power Outage

February 4, 2026
First Nations Chiefs Call out Ottawa Over Pipeline Deal That Doesn’t Mention Water

First Nations Chiefs Call out Ottawa Over Pipeline Deal That Doesn’t Mention Water

January 26, 2026
SaskPower Signs Power Purchase Deal with 50% Indigenous-Owned Solar Farm

SaskPower Signs Power Purchase Deal with 50% Indigenous-Owned Solar Farm

January 19, 2026

Trending Stories

(Julie Dabrusin/Facebook)

EXCLUSIVE: Carbon Tax Exemption for Canada Would Break World Trade Rules, EU Law

November 3, 2026
1.6k
Alberta Environment and Protected Areas Minister Grant Hunter, Alberta Newsroom/flickr

Alberta Accused of Rushing Environmental Law Changes Behind Closed Doors

November 5, 2026
693
Finance Minister François-Philippe Champagne at 2025 Collision Conferencef/flickr

Federal Budget Funds Clean Grid and Energy Efficiency, Touts ‘Investment Supercycle’ Built on Major Projects

November 6, 2026
684

Actions Speak Louder Than Words

by Mitchell Beer
November 2, 2026

…

Follow Us

Copyright 2026 © Energy Mix Productions Inc. All rights reserved.

  • About
  • Contact
  • Privacy Policy and Copyright
  • Cookie Policy
No Result
View All Result
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
    • Climate Glossary
    • What If We Changed the Conversation on Climate Change?
    • Eco-Anxiety
  • About
  • Contact

Copyright 2025 © Smarter Shift Inc. and Energy Mix Productions Inc. All rights reserved.

Manage Cookie Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}
No Result
View All Result
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
    • Climate Glossary
    • What If We Changed the Conversation on Climate Change?
    • Eco-Anxiety
  • About
  • Contact

Copyright 2025 © Smarter Shift Inc. and Energy Mix Productions Inc. All rights reserved.