The Energy Mix
Subscribe
Donate
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
  • About
  • Contact
No Result
View All Result
The Energy Mix
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
  • About
  • Contact
Subscribe
Donate
The Energy Mix
Subscribe

Site C Reports $610-Million Cost Overrun as Eliesen Predicts More to Come

October 6, 2017
Reading time: 2 minutes

Robin/Flickr

Robin/Flickr

The cost of the controversial Site C hydroelectric project in British Columbia has increased by C$610 million, to nearly $9 billion, BC Hydro admitted in a letter posted Wednesday to the Site C Inquiry website.

“Development in the project is expected to increase its cost by 7.3% or $610 million, for a total forecast project cost of $8.945 billion,” CEO Chris O’Reiley told the BC Utilities Commission.

The news prompted Site C critic Marc Eliesen, a former CEO of the provincial utility, to predict the project will be cancelled. It’s currently under review by an independent panel appointed by B.C.’s new provincial government, though construction is continuing while the inquiry proceeds.

Get the latest climate news and analysis, direct to your inbox.

Subscribe Today

View our latest digests

“This is significantly over budget,” Eliesen told National Observer yesterday. “This is a sign of things to come. The entire project has been mismanaged. BC Hydro has not been transparent with the public, and it’s been running into all these difficulties.”

One of those difficulties is that the province no longer needs the electricity the mega-dam would produce.

“If the economics are terrible, the other aspects which are equally important—I’m referring to Indigenous rights and loss of agricultural land—will also be taken into account,” Eliesen said. “I think they will terminate the project.”

In separate correspondence to the Utilities Commission this week, BC Hydro maintained Site C will still be needed to power three liquefied natural gas (LNG) projects—Shell Canada’s LNG Canada project, the Woodfibre LNG project, and a future expansion of FortisBC’s Tilbury LNG storage facility—and possibly a fourth project now undergoing a feasibility study, the Calgary Herald reports.

The letter and an accompanying report are “an attempt to explain why BC Hydro continues to forecast a surge in electricity demand in the province, even though massive LNG projects proposed by Malaysia’s state-owned oil company Petronas and China’s CNOOC Nexen have been cancelled,” the Herald notes. “An explanation is needed because “the commission had specifically asked for an explanation of BC Hydro’s electric load forecast as it relates to LNG projects.”

While the provincial utility continues to project electricity demand based on legacy assumptions about energy development, an analysis in The Tyee comes to a different conclusion.

“BC Hydro has blandly assured the taxpayers that the $8.8-billion Site C dam project scheduled to come online in 2024 is both needed and viable,” notes freelance writer Mitchell Anderson. But “in those seven short years, disruptive energy technologies will upend not only the business case for this outdated megaproject, but perhaps even the need for BC Hydro itself.”







in Carbon Pricing

Trending Stories

More than one-third of the Jasper townsite was destroyed by wildfire in 2024  (Laura Durno/Twitter)
Drought & Wildfires

Climate Change Made High Temperatures Twice as Likely Before Jasper Wildfire

August 22, 2024
2.3k
(File photo by Fibonacci Blue/flickr)
Climate Action

Climate Voices See Complications With Blocking New Oil and Gas

November 10, 2026
680
LNG Canada flarestack (supplied image)
Legal & Regulatory

Lawyer’s Letter Warns Pension Funds Over Potential LNG Investments

November 12, 2026
529

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

I agree to the Terms & Conditions and Privacy Policy.

Get the latest climate news and analysis, direct to your inbox.

Subscribe Today

Fossil Fuel Phaseout. Cutting Off Demand. Every Strategy Needs to Deliver.

by Mitchell Beer
November 15, 2026

…

Follow Us

Site C Reports $610-Million Cost Overrun as Eliesen Predicts More to Come

October 6, 2017
Reading time: 2 minutes

Robin/Flickr

Robin/Flickr

The cost of the controversial Site C hydroelectric project in British Columbia has increased by C$610 million, to nearly $9 billion, BC Hydro admitted in a letter posted Wednesday to the Site C Inquiry website.

“Development in the project is expected to increase its cost by 7.3% or $610 million, for a total forecast project cost of $8.945 billion,” CEO Chris O’Reiley told the BC Utilities Commission.

The news prompted Site C critic Marc Eliesen, a former CEO of the provincial utility, to predict the project will be cancelled. It’s currently under review by an independent panel appointed by B.C.’s new provincial government, though construction is continuing while the inquiry proceeds.

Get the latest climate news and analysis, direct to your inbox.

Subscribe Today

View our latest digests

“This is significantly over budget,” Eliesen told National Observer yesterday. “This is a sign of things to come. The entire project has been mismanaged. BC Hydro has not been transparent with the public, and it’s been running into all these difficulties.”

One of those difficulties is that the province no longer needs the electricity the mega-dam would produce.

“If the economics are terrible, the other aspects which are equally important—I’m referring to Indigenous rights and loss of agricultural land—will also be taken into account,” Eliesen said. “I think they will terminate the project.”

In separate correspondence to the Utilities Commission this week, BC Hydro maintained Site C will still be needed to power three liquefied natural gas (LNG) projects—Shell Canada’s LNG Canada project, the Woodfibre LNG project, and a future expansion of FortisBC’s Tilbury LNG storage facility—and possibly a fourth project now undergoing a feasibility study, the Calgary Herald reports.

The letter and an accompanying report are “an attempt to explain why BC Hydro continues to forecast a surge in electricity demand in the province, even though massive LNG projects proposed by Malaysia’s state-owned oil company Petronas and China’s CNOOC Nexen have been cancelled,” the Herald notes. “An explanation is needed because “the commission had specifically asked for an explanation of BC Hydro’s electric load forecast as it relates to LNG projects.”

While the provincial utility continues to project electricity demand based on legacy assumptions about energy development, an analysis in The Tyee comes to a different conclusion.

“BC Hydro has blandly assured the taxpayers that the $8.8-billion Site C dam project scheduled to come online in 2024 is both needed and viable,” notes freelance writer Mitchell Anderson. But “in those seven short years, disruptive energy technologies will upend not only the business case for this outdated megaproject, but perhaps even the need for BC Hydro itself.”







in Carbon Pricing

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

I agree to the Terms & Conditions and Privacy Policy.

Trending Stories

More than one-third of the Jasper townsite was destroyed by wildfire in 2024  (Laura Durno/Twitter)

Climate Change Made High Temperatures Twice as Likely Before Jasper Wildfire

August 22, 2024
2.3k
(File photo by Fibonacci Blue/flickr)

Climate Voices See Complications With Blocking New Oil and Gas

November 10, 2026
680
LNG Canada flarestack (supplied image)

Lawyer’s Letter Warns Pension Funds Over Potential LNG Investments

November 12, 2026
529

Fossil Fuel Phaseout. Cutting Off Demand. Every Strategy Needs to Deliver.

by Mitchell Beer
November 15, 2026

…

Follow Us

Copyright 2026 © Energy Mix Productions Inc. All rights reserved.

  • About
  • Contact
  • Privacy Policy and Copyright
  • Cookie Policy
No Result
View All Result
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
  • About
  • Contact

Copyright 2025 © Smarter Shift Inc. and Energy Mix Productions Inc. All rights reserved.

Manage Cookie Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}
No Result
View All Result
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
  • About
  • Contact

Copyright 2025 © Smarter Shift Inc. and Energy Mix Productions Inc. All rights reserved.