Turbines at Prince Edward Island’s Hermanville wind farm may be at “high risk of imminent failure,” after two 56-metre blades snapped off one of the structures during high winds last month.
The warning came from a 2022 report from Montreal-based DNV Canada, a consulting firm hired to assess production problems at the C$60-million facility, CBC reports. It found a “severe degree of damage or defect”, including cracked blades and bearings, damage to the systems meant to protect the turbines from lightning strikes, failed or missing components on some turbines, and failures in more than 200 of the blade studs used to hold turbine blades in position.
“In a worst-case scenario, should multiple blade studs fail nearly simultaneously, stud failures may progress and separation of the blade from the turbine could occur,” the DNV report warned.
While the turbine that failed last month was one of three where DNV identified broken blade bolts, the provincial government said that wasn’t what caused the blades to snap. The turbine in question was already out of service due to a failed pitch ram, the component that allows turbine blades to be angled to catch the wind. “Early indications point to this as a potential root cause for the damage in December 2023, but further analysis will be required,” the province told CBC in a statement.
“When Hermanville opened in 2014, the province said it was the first commercial deployment in North America of the Acciona AW 116/3000 model of wind turbine,” CBC writes. But while acknowledging that the design had “a significant track record,” DNV said it didn’t consider the AW 116/3000 a proven model for North America.
Last February, a second consultant, Frontier Power Systems, laid out a plan to retrofit the four of Hermanville’s 10 wind turbines that were out of service. That report “highlighted the urgency of the repairs required,” CBC says, citing “manufacturing flaws” and “major deficiencies” in design and construction.
Frontier’s report said the wind farm could be “largely renewed by the fall of 2023” if the province completed repairs over the summer. But that work was seemingly put on hold when Nordex, the company that merged with the wind farm’s original developer and took over maintenance responsibilities in 2016, said it would complete the work at the PEI Energy Corporation’s expense.
That month, Energy Minister Steven Myers said PEI would cover the $10-million repair bill and try to recoup the funds from Nordex. CBC says the company didn’t respond to a request for comment.
The CBC story includes copies of the DNV Canada and Frontier Power Systems reports.