February 19, 2026 – Ontario’s plan to build the world’s largest nuclear generating station at Wesleyville, near Port Hope, is rapidly emerging as one of the most consequential infrastructure decisions in the province’s history, as well as one of the most controversial.
Ontario Power Generation (OPG) is proposing to generate up to 10,000 megawatts of electricity from as many as 10 reactors, enough to supply millions of homes and support a “rapidly electrifying” economy. But critics warn the massive undertaking could cost well over C$165 billion, and potentially far more, placing unprecedented and unjustified financial risk on taxpayers and electricity ratepayers.
Environmental advocates and local residents say the province has yet to demonstrate the need for a project of this scale or fully examine cheaper alternatives like wind, solar, battery storage, and energy efficiency measures. A briefing circulated by community group Blue Dot Northumberland argues OPG has not released a confirmed design, firm cost estimate, or detailed comparison with lower-cost options. The group wants the federal Impact Assessment Agency to demand that OPG present a “properly scoped” proposal, as required by the Impact Assessment Act.
Rising Nuclear Costs Already Hitting Consumers
The Wesleyville proposal arrives as Ontario faces rising nuclear electricity prices tied to refurbishments of aging reactors. According to Michael Barnard at Clean Technica, OPG has asked the Ontario Energy Board to raise the regulated price it receives for nuclear power from about $78 per megawatt-hour in 2026 to roughly $110/MWh in 2027. Barnard explains that while that headline figure suggests a dramatic jump, the impact on households would be smaller—about an $8 increase on a typical monthly bill—because generation is only one component of electricity costs.
The price hike is largely driven by reduced nuclear output during refurbishment outages at stations including the Darlington and Pickering nuclear generating stations, which has forced fixed operating and financing costs to be spread over fewer units of electricity.
But when nuclear output falls, Ontario relies more heavily on natural gas and imports to fill the gap, exposing the grid to fuel price volatility and emissions increases—a dynamic critics say shows the risks of depending heavily on large, inflexible nuclear plants. So if Ontario is using more gas for flexibility, Barnard says this brings fuel price risks and emissions that didn’t matter as much when gas was used less. Other critics like Seniors for Climate Action Now (SCAN) outlined in a statement [pdf] that such reliance leads to “false claims on net zero and climate impact.”
Paying Up Front for Power Not Yet Built
The cost debate is intensifying after reporting revealed that Ontarians are increasingly paying for nuclear projects before they produce electricity. Mark Winfield, an environmental policy professor at York University, said financing arrangements for new nuclear construction—including a reactor at Darlington and the refurbishment work at Pickering—were a major factor behind a 29% electricity rate increase that took effect in November.
That increase was partially offset by a near doubling of provincial electricity rebates, now costing about $2 billion annually and funded from general tax revenues. In effect, Winfield argues, taxpayers have already begun covering capital costs for projects whose total price tag could reach tens of billions of dollars.
He estimates Ontario’s electricity subsidy programs now cost roughly $8.5 billion per year—comparable to nearly two-thirds of the provincial deficit and exceeding spending in some major public sectors. If additional nuclear projects proceed, including Wesleyville and expansions at the Bruce Power nuclear site, the annual cost of subsidies could climb to $20 billion, potentially forcing tax hikes, deeper deficits, or cuts to services such as health care and education.
Need, Alternatives, and Risk
The Wesleyville project raises fundamental questions about whether nuclear expansion is the most affordable path to a low-carbon grid, opponents say. Independent analyses cited by environmental groups suggest wind and solar power, paired with battery storage, could produce electricity at less than half the cost of nuclear generation.
Critics also point to unresolved issues surrounding radioactive waste disposal, accident liability, and the long-term environmental footprint of large nuclear facilities.
Health and safety concerns have also been raised. While regulators maintain properly operated plants pose minimal risk, the SCAN briefing warns that severe accidents, though unlikely, could have long-lasting consequences for nearby communities.
The site’s proximity to Lake Ontario has prompted questions about thermal pollution from discharged cooling water and potential impacts on aquatic ecosystems.
Security considerations are another factor. Large nuclear installations are considered critical infrastructure and potential targets in geopolitical conflicts, leading some analysts to argue that a decentralized energy system based on renewables could be more resilient.
Province Sees Nuclear as a Backbone
Supporters of the project, including provincial officials, contend nuclear energy remains essential to meeting Ontario’s growing electricity demand while maintaining low greenhouse gas emissions. But independent analysis by Ontario’s electricity market operator suggests wind, solar, and batteries could help meet the province’s future energy needs cheaply, though that modelling exercise left out key costs like transmission, labour, and supply chain limits.
Electrification of transportation, heating, and industry is expected to significantly increase power consumption over the coming decades, and the province says nuclear plants provide stable, around-the-clock generation that intermittent renewables cannot deliver alone. But historical patterns show nuclear projects tend to run far over budget and behind schedule, such as the Darlington station’s original construction, which nearly doubled its cost. The province says the plant’s recent refurbishment came in slightly under budget at $9.29 billion instead of the estimated $9.4 billion.
“It’s not too late for Ontario to substitute a portion of their planned natural gas and nuclear generation with more affordable options,” the Pembina Institute wrote in December.
The province is also framing Wesleyville as an economic development opportunity that could create thousands of jobs and anchor supply chains for Canada’s nuclear sector.











An excellent and an essential article for not only those of us in Northumberland County who are being directly impacted by this mega nuclear project but also to all people who will pay an exorbitant price financially, health wise and as a result of the loss of biodiversity and farmland. The people of Ontario and of Canada will shoulder the burdens while most of the profits will be reaped by US investors.
Hi Bob, thank you so much for reading and thank you for your tireless efforts, it’s an honour to be part of keeping Ontarians informed of the many moving parts their province.
I was thinking along the same
Lines https://open.substack.com/pub/waterkeepermark/p/ontarios-2026-nuclear-expansion-why?r=1w2090&utm_medium=ios
This is a really thought-provoking article — as Ontario pushes ahead with what could be the world’s largest nuclear generating station at Wesleyville, it’s crucial to weigh not just the clean-energy potential but also the rising cost risks and long-term affordability for taxpayers and ratepayers.
I’d hope to see a middle ground in this debate. I believe that nuclear energy has to pay a pivotal role in Ontario’s future economy. An expanded grid is essential for important objectives like increased investments in manufacturing, carbon emission reduction , powering EVs, AI enterprises and the new high frequency rail corridor from Toronto to Quebec city. The Wesleyville site is well suited to that end. However, I also believe solely focusing on nuclear power generation is wrong headed and a monopoly for OPG is particularly hazardous. The government should diversify both how electricity is produced and what companies they do business with.
Mark, would you consider that the pragmatic middle ground you’re looking for is to prioritize the various options according to least cost, fastest deployment, and maximum local resilience in a climate change-driven grid emergency? Those criteria don’t just make sense for communities. With the possible/probable exception of the adjectival reference to climate change, they’re also the criteria that site selectors bring to the table when they’re looking to locate new data centres, advanced manufacturing sites, or other new-economy job creators. An honest comparison of nuclear against renewables + storage — based on today’s experience, not historical data from 10, five, or even two years ago — will give you a good, evidence-driven sense of where nuclear fits in the overall picture. It may not be what you expect.
Out of curiosity where is your source for the estimated $165 billion cost?