The Energy Mix
Subscribe
Donate
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
    • Climate Glossary
    • What If We Changed the Conversation on Climate Change?
    • Eco-Anxiety
  • About
  • Contact
No Result
View All Result
The Energy Mix
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
    • Climate Glossary
    • What If We Changed the Conversation on Climate Change?
    • Eco-Anxiety
  • About
  • Contact
Subscribe
Donate
The Energy Mix
Subscribe

Ontario Confirms $12.8-Billion Darlington Rebuild as Critics Predict Cost Overruns

January 13, 2016
Reading time: 2 minutes

Nuclear Regulatory Commission/Flickr

Nuclear Regulatory Commission/Flickr

Óðinn/wikimedia commons
Óðinn/wikimedia commons

Ontario is pushing ahead with a C$12.8-billion reconstruction project at its Darlington nuclear station that will extend the plant’s operating life from 2020 to 2050.

To maintain the province’s electricity supply during the rebuild, Ontario Power Generation will continue operating the Pickering nuclear station through 2024. That decision “will save up to $600 million compared to running natural gas-fired plants or [relying on] imports to fill the gap,” the Toronto Star reports.

Get the latest climate news and analysis, direct to your inbox.

Subscribe Today

View our latest digests

“The price is right and it is emissions-free,” said Energy Minister Bob Chiarelli, adding that the two projects will create 8,800 jobs per year over 10 years and extend 4,500 other jobs at Pickering.

For months, the Ontario Clean Air Alliance and Montreal-based Équiterre have argued that Ontario could import power from Quebec hydro plants for far less than the cost of refurbishing Darlington. This week, Chiarelli said that approach would require expensive transmission upgrades. “It’s not doable and it’s not feasible,” he told media.

Ontario Green Party leader Mike Schreiner called it “outrageously irresponsible” to “commit billions of your dollars to a project without a review of costs and alternatives,” adding that “no nuclear project in Ontario’s history has been delivered on time or on budget.”

At 7.2 to 8.1¢/kWh (before cost overruns), the projected cost of electricity from the refurbished Darlington plant will be 30 to 45% higher than average nuclear electricity costs of 5.6¢/kWh in 2014, the Clean Air Alliance noted in a release Monday.

“The Darlington deal also explicitly recognizes that once you open up 30-year-old reactors, costs can—and almost certainly will—skyrocket,” OCAA notes. “The new Darlington deal includes a $1.7-billion contingency fund—recognition of just what a high-risk project this truly is. No renewable power, efficiency, or water power import deal signed by Ontario includes a giant contingency fund.”







in Canada, Fossil Fuels, Jobs & Training, Nuclear, Regions, Subnational

Trending Stories

Alberta Premier Danielle Smith and Minister of Technology and Innovation Nate Glubish introduced, at a news conference in Edmonton on December 4, 2024, the province’s new data strategy. (photography by Chris Schwarz/Government of Alberta)
Data Centres & Tech

Smith Tells Albertans to ‘Lock In’ Power Prices Before Meta Data Centre Joins Grid

September 1, 2026
39.4k
Jay Phagan/flickr
Pipelines / Rail Transport

West Coast Pipeline Won’t Recoup Its $43.7B Cost as Global Oil Demand Weakens

September 2, 2026
2k
@5thAdmiralFrank
/Twitter
Carbon Levels & Measurement

‘Call to Apathy, Not to Arms’ as UN Warns Climate Overshoot Is Inevitable, Downplays Fossil Phaseout

September 3, 2026
403

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

I agree to the Terms & Conditions and Privacy Policy.

Get the latest climate news and analysis, direct to your inbox.

Subscribe Today

The Better Ideas Show: How the Clean Climate Economy Protects Canada’s Sovereignty

by Mitchell Beer
August 30, 2026

…

Follow Us

Ontario Confirms $12.8-Billion Darlington Rebuild as Critics Predict Cost Overruns

January 13, 2016
Reading time: 2 minutes

Nuclear Regulatory Commission/Flickr

Nuclear Regulatory Commission/Flickr

Óðinn/wikimedia commons
Óðinn/wikimedia commons

Ontario is pushing ahead with a C$12.8-billion reconstruction project at its Darlington nuclear station that will extend the plant’s operating life from 2020 to 2050.

To maintain the province’s electricity supply during the rebuild, Ontario Power Generation will continue operating the Pickering nuclear station through 2024. That decision “will save up to $600 million compared to running natural gas-fired plants or [relying on] imports to fill the gap,” the Toronto Star reports.

Get the latest climate news and analysis, direct to your inbox.

Subscribe Today

View our latest digests

“The price is right and it is emissions-free,” said Energy Minister Bob Chiarelli, adding that the two projects will create 8,800 jobs per year over 10 years and extend 4,500 other jobs at Pickering.

For months, the Ontario Clean Air Alliance and Montreal-based Équiterre have argued that Ontario could import power from Quebec hydro plants for far less than the cost of refurbishing Darlington. This week, Chiarelli said that approach would require expensive transmission upgrades. “It’s not doable and it’s not feasible,” he told media.

Ontario Green Party leader Mike Schreiner called it “outrageously irresponsible” to “commit billions of your dollars to a project without a review of costs and alternatives,” adding that “no nuclear project in Ontario’s history has been delivered on time or on budget.”

At 7.2 to 8.1¢/kWh (before cost overruns), the projected cost of electricity from the refurbished Darlington plant will be 30 to 45% higher than average nuclear electricity costs of 5.6¢/kWh in 2014, the Clean Air Alliance noted in a release Monday.

“The Darlington deal also explicitly recognizes that once you open up 30-year-old reactors, costs can—and almost certainly will—skyrocket,” OCAA notes. “The new Darlington deal includes a $1.7-billion contingency fund—recognition of just what a high-risk project this truly is. No renewable power, efficiency, or water power import deal signed by Ontario includes a giant contingency fund.”







in Canada, Fossil Fuels, Jobs & Training, Nuclear, Regions, Subnational

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

I agree to the Terms & Conditions and Privacy Policy.

Trending Stories

Alberta Premier Danielle Smith and Minister of Technology and Innovation Nate Glubish introduced, at a news conference in Edmonton on December 4, 2024, the province’s new data strategy. (photography by Chris Schwarz/Government of Alberta)

Smith Tells Albertans to ‘Lock In’ Power Prices Before Meta Data Centre Joins Grid

September 1, 2026
39.4k
Jay Phagan/flickr

West Coast Pipeline Won’t Recoup Its $43.7B Cost as Global Oil Demand Weakens

September 2, 2026
2k
@5thAdmiralFrank
/Twitter

‘Call to Apathy, Not to Arms’ as UN Warns Climate Overshoot Is Inevitable, Downplays Fossil Phaseout

September 3, 2026
403

The Better Ideas Show: How the Clean Climate Economy Protects Canada’s Sovereignty

by Mitchell Beer
August 30, 2026

…

Follow Us

Copyright 2026 © Energy Mix Productions Inc. All rights reserved.

  • About
  • Contact
  • Privacy Policy and Copyright
  • Cookie Policy
No Result
View All Result
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
    • Climate Glossary
    • What If We Changed the Conversation on Climate Change?
    • Eco-Anxiety
  • About
  • Contact

Copyright 2025 © Smarter Shift Inc. and Energy Mix Productions Inc. All rights reserved.

Manage Cookie Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}
No Result
View All Result
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
    • Climate Glossary
    • What If We Changed the Conversation on Climate Change?
    • Eco-Anxiety
  • About
  • Contact

Copyright 2025 © Smarter Shift Inc. and Energy Mix Productions Inc. All rights reserved.