Amid rising consumer electricity prices in the United States, Google is bucking the artificial intelligence data centre trend of putting pressure on utilities for increasingly more power.
Michael Terrell, Google’s Advanced Energy lead, announced two new utility agreements with Indiana Michigan Power and the Tennessee Valley Authority that rely instead on demand response, a strategy that schedules and manages energy-intensive computing workloads to boost energy efficiency.
“Research shows that even a small amount of flexibility for large energy loads, like machine learning, during peak times can reduce the need to build new power plants while accommodating new energy loads much faster—making more efficient use of existing generation,” he wrote on LinkedIn.
When a grid operator notifies Google of a local grid event, meaning a constraint or interruption caused by things like extreme weather, it can supply “hour-by-hour instructions for specified data centres to limit non-urgent compute tasks for the duration of the grid event.”
Those non-urgent tasks can be rescheduled or rerouted to a data centre elsewhere, Terrell said in the announcement.
He cited a Duke University study that found flexibility is “a promising, near-term strategy for addressing structural transformations in the U.S. electric power system.”
One of the biggest misconceptions about data centres is the “five nines”, or 99.999% uptime standard, Tyler Norris, one of the Duke study authors, wrote on social media. That requirement is meant to be a customer guarantee, but it has little to do with capacity utilization.
“Even AI-specialized data centres don’t operate anywhere near 99.999% utilization,” Norris said. “Capacity utilization rates are closer to 50%, and up to 60-70% on high end.”
New data centres can increasingly “schedule” their non-utilization during periods of highest grid stress or use some combination of onsite storage, thermal generation, and/or time-shifting to enable access to more grid power, Norris added.
Terrell said Google has also developed the capability to shift computing tasks to grids running on the cleanest energy sources.
“None of this would have been possible without our 24/7 carbon-free energy ambition, which made us think holistically and creatively about how to align our own hourly energy consumption with the needs of electricity grids,” he said.
In Nevada, Google backed a geothermal plant for its data centres, which now supplies electricity to local utilities. And the tech giant has just selected Tennessee for an advanced nuclear power plant that it will be counting on to power its southeastern U.S. data centres starting in 2030.
The announcement comes as NPR reports that electricity prices in the U.S. are rising at more than double the rate of inflation, and that AI data centres are adding to the problem. Electricity prices were up 5.5% over the last year, while the Consumer Price Index went up 2.7%, according to the U.S. Bureau of Labor Statistics.
The U.S. Energy Department predicts [pdf] that by 2026, data centres and other commercial users will consume more electricity than households for the first time on record. Utilities have proposed [pdf] $29 billion worth of rate hikes so far this year, compared to $12 billion last year, says the electricity policy research group PowerLines.
“Costs are increasing too fast,” Johns Hopkins scholar Abraham Silverman told Heatmap. “The amount of infrastructure we need to build is too much. We need to prioritize, and we need to make this data centre expansion affordable for consumers.”
“You can’t have multi-billion-dollar rate increases year over year.”
The pressure on utilities can drive “hasty decisions like overbuilding new natural gas capacity,” warned RMI in a recent report. But PowerLines founder and executive director Charles Hua told Heatmap that data centres “could essentially piggyback on existing grid infrastructure” if they commit to not drawing power at times of high demand.
“Creating a system where data centres can connect to the grid sooner if they promise to be flexible about power consumption would require immense institutional change for states, utilities, regulators, and power markets,” Hua said.
Norris said jurisdictions aren’t set up to acknowledge and offer incentives for flexible loads.
So state governments should rewrite utility regulations and tie tax incentives to data centre flexibility, Silverman suggested.
“Speed is of the essence—not just to be able to link up more data centres, but also to avoid a political firestorm around rising electricity rates,” he said, warning of a growing data centre backlash.