The Energy Mix
Subscribe
Donate
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
  • About
  • Contact
No Result
View All Result
The Energy Mix
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
  • About
  • Contact
Subscribe
Donate
The Energy Mix
Subscribe

Community Pushback Blocks $64B in U.S. Data Centre Development

July 13, 2026
Reading time: 4 minutes
Full Story: The Energy Mix
Jody MacPherson

Rebecca MacIntosh/YouTube

Rebecca MacIntosh/YouTube

Community opposition blocked or delayed US$64 billion of data centre projects in the United States in less than a year, yet community concerns do not make the top-four list of considerations for data centre proponents when they pick a location.

Bloom Energy, a California-based multinational that specializes in onsite fuel cell power systems, conducted a survey of 156 data centre decision-makers, and reviewed public announcements and conversations with industry leaders.

The survey found that power availability remains the biggest challenge to industry growth plans, though community scrutiny of rising electricity prices, water consumption, and grid reliability has become the second biggest barrier to development.

Bloom Chief Marketing Officer Natalie Sunderland said in a news release that “solutions that reduce strain on local infrastructure while helping developers bring new capacity online faster—such as clean onsite power—will play an important role” in moving future projects forward.

“We believe the winners in the next phase of AI buildout will be those that can grow in a way that works for both operators and the communities that host them.”

The report finds that developers deal with a long list of objections rather than a single issue. The top three are rising electricity prices, water consumption, and grid reliability. Other issues include traffic and construction disruption, limited local economic benefits, carbon emissions, land use and visual impact, noise, and air quality.

Get the latest climate news and analysis, direct to your inbox.

Subscribe Today

View our latest digests

However, only about half of the data centre decision-makers surveyed said they were holding public forums or investing in local initiatives, while recent national polling shows that only 33% of developers are addressing grid reliability, and only 29% are responding to water consumption concerns. The report authors suggest “a disconnect between engagement efforts and community priorities.”

About 61% of respondents said they would rather deploy onsite power, usually fossil gas, than relocate to a site with power, but only about one-third of those U.S. data centre projects are expected to incorporate carbon capture, utilization, and storage (CCUS), projected to grow to more than 40% by 2035.

Another report, authored by the Environmental Integrity Project (EIP), found at least 74 gas-fired power plants on tap to provide energy for data centres across the U.S. would release nearly 662 million tons per year of greenhouse gas pollution, equal to 140 million cars and trucks driving for a year.

S&P Global estimated in 2024 that the clamour for electricity from data centres could increase gas demand by up to 170 million cubic metres per day by 2030, which would mean even more emissions from leaks and the operation of facilities such as new pipelines, processing plants, and storage facilities.

EIP reported that 89% of the power plants are slated for low-income communities already saddled with pollution and premature death and would worsen public health by releasing 159,142 tons a year of air pollutants, including 44,281 tons of nitrogen oxides that contribute to smog and lung damage, and 32,684 tons of fine particulate matter, which can trigger heart and asthma attacks.

Communities “deserve better than decades of toxic pollution, parched streambeds, and climate chaos,” Clean Air Council Executive Director Alex Bomstein said in a news release.

“In their wholehearted embrace of dirty and outdated gas power, data centre developers are announcing to the public that they don’t care about us.”

Water consumption was one of the top three community concerns identified in the Bloom report, and EIP found that power plants use between 75-92% of all the water needed to keep data centres running. More than half of the water used in data centres comes from potable water supplies and two-thirds of U.S. data centres in the last four years have been built or planned in water-stressed regions, according to EIP.

“Water conservation and better location planning are important to protect public water supplies from this thirsty industry,” the Bloom report’s authors wrote.

At the time the Bloom Energy report was released in June, at least 18 state bills and 86 local moratoriums were proposed across the U.S., while industry was forecasting more than a doubling of data centre power demand by 2030, to between 700 and 1,200 trillion watt hours (TWh).

The Electric Power Research Institute Inc., a non-profit energy research and development organization, reported in its 2026 projection that U.S. data centres could double or even triple their power consumption to 9–17% of the nation’s electricity by 2030, compared to the 4-5% it uses now.

Access to power is the number one concern for data centre developers as the demands for more intense computing power increase. The “inference” work, where a trained machine learning model draws conclusions from brand new data, now uses more than half of overall artificial intelligence computing power required.

Power for “training,” or showing examples of desired inputs and outputs, is not being displaced, but is growing alongside inference, according to the Bloom Energy report.

In May, the North American Electric Reliability Corporation (NERC), a not-for-profit, international regulatory authority, issued a Level 3 Alert, its highest alert rating, asking utilities to take action to “address immediate risks posed by computational loads interfacing with the bulk power system, threatening reliability.” Computational loads include AI training, cryptocurrency mining, and traditional data centre uses.

“NERC observed customer-initiated large load reductions and significant oscillations that occur in seconds, leaving little or no room for real-time responses, threatening bulk power system reliability,” NERC wrote in a statement that called the challenge to the grid “unprecedented.” Registered utilities have until August 3 to submit their responses to the NERC, although the request is non-binding.







in CCS & Negative Emissions, Climate Action, Data Centres & Tech, Health & Safety, Heat & Power, Legal & Regulatory, Oil & Gas, Power Grids, United States

Trending Stories

More than one-third of the Jasper townsite was destroyed by wildfire in 2024  (Laura Durno/Twitter)
Drought & Wildfires

Climate Change Made High Temperatures Twice as Likely Before Jasper Wildfire

August 22, 2024
2.2k
Finance Minister François-Philippe Champagne at 2025 Collision Conferencef/flickr
Finance & Investment

Federal Budget Funds Clean Grid and Energy Efficiency, Touts ‘Investment Supercycle’ Built on Major Projects

November 6, 2026
992
Alberta Environment and Protected Areas Minister Grant Hunter, Alberta Newsroom/flickr
Legal & Regulatory

Alberta Accused of Rushing Environmental Law Changes Behind Closed Doors

November 5, 2026
979

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

I agree to the Terms & Conditions and Privacy Policy.

Get the latest climate news and analysis, direct to your inbox.

Subscribe Today

Related Articles

Grid CEO Wants to ‘Check Engine’ as AI Power Demand Leads to ‘Frankenstein Financing’

Grid CEO Wants to ‘Check Engine’ as AI Power Demand Leads to ‘Frankenstein Financing’

January 7, 2026
#Encore: EXCLUSIVE: O’Leary’s Gas-Powered Data Centre Emissions Could Wipe Out Alberta’s Coal Phaseout Gains

#Encore: EXCLUSIVE: O’Leary’s Gas-Powered Data Centre Emissions Could Wipe Out Alberta’s Coal Phaseout Gains

December 24, 2025
Finland, Sweden Warm Up to Data Centre District Heat Amid Lingering Sustainability Concerns

Finland, Sweden Warm Up to Data Centre District Heat Amid Lingering Sustainability Concerns

December 10, 2025

An ‘Extinction-Level Event’ for Trump. A Renewable Energy Surge. A Spiralling Climate Crisis. Is Your Head Spinning Yet?

by Mitchell Beer
November 8, 2026

…

Follow Us

Community Pushback Blocks $64B in U.S. Data Centre Development

July 13, 2026
Reading time: 4 minutes
Full Story: The Energy Mix
Jody MacPherson

Rebecca MacIntosh/YouTube

Rebecca MacIntosh/YouTube

Community opposition blocked or delayed US$64 billion of data centre projects in the United States in less than a year, yet community concerns do not make the top-four list of considerations for data centre proponents when they pick a location.

Bloom Energy, a California-based multinational that specializes in onsite fuel cell power systems, conducted a survey of 156 data centre decision-makers, and reviewed public announcements and conversations with industry leaders.

The survey found that power availability remains the biggest challenge to industry growth plans, though community scrutiny of rising electricity prices, water consumption, and grid reliability has become the second biggest barrier to development.

Bloom Chief Marketing Officer Natalie Sunderland said in a news release that “solutions that reduce strain on local infrastructure while helping developers bring new capacity online faster—such as clean onsite power—will play an important role” in moving future projects forward.

“We believe the winners in the next phase of AI buildout will be those that can grow in a way that works for both operators and the communities that host them.”

The report finds that developers deal with a long list of objections rather than a single issue. The top three are rising electricity prices, water consumption, and grid reliability. Other issues include traffic and construction disruption, limited local economic benefits, carbon emissions, land use and visual impact, noise, and air quality.

Get the latest climate news and analysis, direct to your inbox.

Subscribe Today

View our latest digests

However, only about half of the data centre decision-makers surveyed said they were holding public forums or investing in local initiatives, while recent national polling shows that only 33% of developers are addressing grid reliability, and only 29% are responding to water consumption concerns. The report authors suggest “a disconnect between engagement efforts and community priorities.”

About 61% of respondents said they would rather deploy onsite power, usually fossil gas, than relocate to a site with power, but only about one-third of those U.S. data centre projects are expected to incorporate carbon capture, utilization, and storage (CCUS), projected to grow to more than 40% by 2035.

Another report, authored by the Environmental Integrity Project (EIP), found at least 74 gas-fired power plants on tap to provide energy for data centres across the U.S. would release nearly 662 million tons per year of greenhouse gas pollution, equal to 140 million cars and trucks driving for a year.

S&P Global estimated in 2024 that the clamour for electricity from data centres could increase gas demand by up to 170 million cubic metres per day by 2030, which would mean even more emissions from leaks and the operation of facilities such as new pipelines, processing plants, and storage facilities.

EIP reported that 89% of the power plants are slated for low-income communities already saddled with pollution and premature death and would worsen public health by releasing 159,142 tons a year of air pollutants, including 44,281 tons of nitrogen oxides that contribute to smog and lung damage, and 32,684 tons of fine particulate matter, which can trigger heart and asthma attacks.

Communities “deserve better than decades of toxic pollution, parched streambeds, and climate chaos,” Clean Air Council Executive Director Alex Bomstein said in a news release.

“In their wholehearted embrace of dirty and outdated gas power, data centre developers are announcing to the public that they don’t care about us.”

Water consumption was one of the top three community concerns identified in the Bloom report, and EIP found that power plants use between 75-92% of all the water needed to keep data centres running. More than half of the water used in data centres comes from potable water supplies and two-thirds of U.S. data centres in the last four years have been built or planned in water-stressed regions, according to EIP.

“Water conservation and better location planning are important to protect public water supplies from this thirsty industry,” the Bloom report’s authors wrote.

At the time the Bloom Energy report was released in June, at least 18 state bills and 86 local moratoriums were proposed across the U.S., while industry was forecasting more than a doubling of data centre power demand by 2030, to between 700 and 1,200 trillion watt hours (TWh).

The Electric Power Research Institute Inc., a non-profit energy research and development organization, reported in its 2026 projection that U.S. data centres could double or even triple their power consumption to 9–17% of the nation’s electricity by 2030, compared to the 4-5% it uses now.

Access to power is the number one concern for data centre developers as the demands for more intense computing power increase. The “inference” work, where a trained machine learning model draws conclusions from brand new data, now uses more than half of overall artificial intelligence computing power required.

Power for “training,” or showing examples of desired inputs and outputs, is not being displaced, but is growing alongside inference, according to the Bloom Energy report.

In May, the North American Electric Reliability Corporation (NERC), a not-for-profit, international regulatory authority, issued a Level 3 Alert, its highest alert rating, asking utilities to take action to “address immediate risks posed by computational loads interfacing with the bulk power system, threatening reliability.” Computational loads include AI training, cryptocurrency mining, and traditional data centre uses.

“NERC observed customer-initiated large load reductions and significant oscillations that occur in seconds, leaving little or no room for real-time responses, threatening bulk power system reliability,” NERC wrote in a statement that called the challenge to the grid “unprecedented.” Registered utilities have until August 3 to submit their responses to the NERC, although the request is non-binding.







in CCS & Negative Emissions, Climate Action, Data Centres & Tech, Health & Safety, Heat & Power, Legal & Regulatory, Oil & Gas, Power Grids, United States

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

I agree to the Terms & Conditions and Privacy Policy.

Related Articles

Grid CEO Wants to ‘Check Engine’ as AI Power Demand Leads to ‘Frankenstein Financing’

Grid CEO Wants to ‘Check Engine’ as AI Power Demand Leads to ‘Frankenstein Financing’

January 7, 2026
#Encore: EXCLUSIVE: O’Leary’s Gas-Powered Data Centre Emissions Could Wipe Out Alberta’s Coal Phaseout Gains

#Encore: EXCLUSIVE: O’Leary’s Gas-Powered Data Centre Emissions Could Wipe Out Alberta’s Coal Phaseout Gains

December 24, 2025
Finland, Sweden Warm Up to Data Centre District Heat Amid Lingering Sustainability Concerns

Finland, Sweden Warm Up to Data Centre District Heat Amid Lingering Sustainability Concerns

December 10, 2025

Trending Stories

More than one-third of the Jasper townsite was destroyed by wildfire in 2024  (Laura Durno/Twitter)

Climate Change Made High Temperatures Twice as Likely Before Jasper Wildfire

August 22, 2024
2.2k
Finance Minister François-Philippe Champagne at 2025 Collision Conferencef/flickr

Federal Budget Funds Clean Grid and Energy Efficiency, Touts ‘Investment Supercycle’ Built on Major Projects

November 6, 2026
992
Alberta Environment and Protected Areas Minister Grant Hunter, Alberta Newsroom/flickr

Alberta Accused of Rushing Environmental Law Changes Behind Closed Doors

November 5, 2026
979

An ‘Extinction-Level Event’ for Trump. A Renewable Energy Surge. A Spiralling Climate Crisis. Is Your Head Spinning Yet?

by Mitchell Beer
November 8, 2026

…

Follow Us

Copyright 2026 © Energy Mix Productions Inc. All rights reserved.

  • About
  • Contact
  • Privacy Policy and Copyright
  • Cookie Policy
No Result
View All Result
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
  • About
  • Contact

Copyright 2025 © Smarter Shift Inc. and Energy Mix Productions Inc. All rights reserved.

Manage Cookie Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}
No Result
View All Result
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
  • About
  • Contact

Copyright 2025 © Smarter Shift Inc. and Energy Mix Productions Inc. All rights reserved.