The Energy Mix
Subscribe
Donate
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
  • About
  • Contact
No Result
View All Result
The Energy Mix
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
  • About
  • Contact
Subscribe
Donate
The Energy Mix
Subscribe

Coastal GasLink Faces Delay as LNG Canada Disputes Cost Overruns, Missed Deadlines

July 29, 2021
Reading time: 2 minutes
Full Story: The Canadian Press @CdnPressNews
Author: Amanda Stephenson @AmandaMsteph

Coastal GasLink/Twitter

Coastal GasLink/Twitter

The completion of the controversial Coastal GasLink pipeline could be delayed if TC Energy can’t resolve an ongoing dispute with LNG Canada over project costs, the Calgary-based company said Thursday.

TC Energy chief executive François Poirier said construction of Coastal GasLink—which TC Energy is building to deliver natural gas from northeastern B.C. to the LNG Canada facility in Kitimat, British Columbia—is nearly 50% complete and making good progress after a delay earlier this year due to COVID-19 public health restrictions, The Canadian Press reports.

But now, the company is in a disagreement with LNG Canada over escalating costs and project scheduling, Poirier said.

Get the latest climate news and analysis, direct to your inbox.

Subscribe Today

View our latest digests

“While commercial discussions are ongoing and we remain committed to successfully completing the project, we are nearing a critical stage that requires resolution of the outstanding issues,” he told analysts on a conference call.

LNG Canada selected TC Energy in 2011 to design, build, own, and operate Coastal GasLink. The 670-kilometre pipeline is intended to move 2.1 billion cubic feet per day (bcf/d) of natural gas through unceded Indigenous territory to LNG Canada’s terminal, where it will be liquified for export to global markets.

In an emailed statement, LNG Canada said TC Energy has proposed cost increases and schedule performance that are “well beyond” what the two companies agreed to when LNG Canada made its final investment decision in October 2018, CP says.

“We have been working hard with TC Energy to understand the reasons for the increase in cost and schedule, and we have provided recommendations on improved execution efficiency,” LNG Canada said in its statement. “Our priorities are on a pipeline that is constructed safely and on schedule, under competitive terms, in order to deliver this critical infrastructure.”

Preliminary construction on Coastal GasLink began in 2019, and the project is currently slated to be complete in 2023.

Also on Thursday, TC Energy reported lower net profits in its latest quarter due to the cancellation of the Keystone XL export oil pipeline. The company’s financial results included a C$2-million charge for Keystone, along with a $408-million gain for selling part of its stake in Coastal GasLink.

The company says its net financial hit from the Keystone XL termination was $1.1 billion as of the end of the quarter. It took an after-tax charge of $2.2 billion last quarter. [Which totally explains why TC Energy is claiming $15 billion in damages in its trade complaint against the United States—Ed.]

This report by The Canadian Press was first published July 29, 2021.







in Canada, Community Climate Finance, Fossil Fuels, Fracking & LNG, Indigenous Rights & Reconciliation, Pipelines / Rail Transport, Regions

Trending Stories

More than one-third of the Jasper townsite was destroyed by wildfire in 2024  (Laura Durno/Twitter)
Drought & Wildfires

Climate Change Made High Temperatures Twice as Likely Before Jasper Wildfire

August 22, 2024
2.3k
(File photo by Fibonacci Blue/flickr)
Climate Action

Climate Voices See Complications With Blocking New Oil and Gas

November 10, 2026
700
LNG Canada flarestack (supplied image)
Legal & Regulatory

Lawyer’s Letter Warns Pension Funds Over Potential LNG Investments

November 12, 2026
533

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

I agree to the Terms & Conditions and Privacy Policy.

Get the latest climate news and analysis, direct to your inbox.

Subscribe Today

Fossil Fuel Phaseout. Cutting Off Demand. Every Strategy Needs to Deliver.

by Mitchell Beer
November 15, 2026

…

Follow Us

Coastal GasLink Faces Delay as LNG Canada Disputes Cost Overruns, Missed Deadlines

July 29, 2021
Reading time: 2 minutes
Full Story: The Canadian Press @CdnPressNews
Author: Amanda Stephenson @AmandaMsteph

Coastal GasLink/Twitter

Coastal GasLink/Twitter

The completion of the controversial Coastal GasLink pipeline could be delayed if TC Energy can’t resolve an ongoing dispute with LNG Canada over project costs, the Calgary-based company said Thursday.

TC Energy chief executive François Poirier said construction of Coastal GasLink—which TC Energy is building to deliver natural gas from northeastern B.C. to the LNG Canada facility in Kitimat, British Columbia—is nearly 50% complete and making good progress after a delay earlier this year due to COVID-19 public health restrictions, The Canadian Press reports.

But now, the company is in a disagreement with LNG Canada over escalating costs and project scheduling, Poirier said.

Get the latest climate news and analysis, direct to your inbox.

Subscribe Today

View our latest digests

“While commercial discussions are ongoing and we remain committed to successfully completing the project, we are nearing a critical stage that requires resolution of the outstanding issues,” he told analysts on a conference call.

LNG Canada selected TC Energy in 2011 to design, build, own, and operate Coastal GasLink. The 670-kilometre pipeline is intended to move 2.1 billion cubic feet per day (bcf/d) of natural gas through unceded Indigenous territory to LNG Canada’s terminal, where it will be liquified for export to global markets.

In an emailed statement, LNG Canada said TC Energy has proposed cost increases and schedule performance that are “well beyond” what the two companies agreed to when LNG Canada made its final investment decision in October 2018, CP says.

“We have been working hard with TC Energy to understand the reasons for the increase in cost and schedule, and we have provided recommendations on improved execution efficiency,” LNG Canada said in its statement. “Our priorities are on a pipeline that is constructed safely and on schedule, under competitive terms, in order to deliver this critical infrastructure.”

Preliminary construction on Coastal GasLink began in 2019, and the project is currently slated to be complete in 2023.

Also on Thursday, TC Energy reported lower net profits in its latest quarter due to the cancellation of the Keystone XL export oil pipeline. The company’s financial results included a C$2-million charge for Keystone, along with a $408-million gain for selling part of its stake in Coastal GasLink.

The company says its net financial hit from the Keystone XL termination was $1.1 billion as of the end of the quarter. It took an after-tax charge of $2.2 billion last quarter. [Which totally explains why TC Energy is claiming $15 billion in damages in its trade complaint against the United States—Ed.]

This report by The Canadian Press was first published July 29, 2021.







in Canada, Community Climate Finance, Fossil Fuels, Fracking & LNG, Indigenous Rights & Reconciliation, Pipelines / Rail Transport, Regions

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

I agree to the Terms & Conditions and Privacy Policy.

Trending Stories

More than one-third of the Jasper townsite was destroyed by wildfire in 2024  (Laura Durno/Twitter)

Climate Change Made High Temperatures Twice as Likely Before Jasper Wildfire

August 22, 2024
2.3k
(File photo by Fibonacci Blue/flickr)

Climate Voices See Complications With Blocking New Oil and Gas

November 10, 2026
700
LNG Canada flarestack (supplied image)

Lawyer’s Letter Warns Pension Funds Over Potential LNG Investments

November 12, 2026
533

Fossil Fuel Phaseout. Cutting Off Demand. Every Strategy Needs to Deliver.

by Mitchell Beer
November 15, 2026

…

Follow Us

Copyright 2026 © Energy Mix Productions Inc. All rights reserved.

  • About
  • Contact
  • Privacy Policy and Copyright
  • Cookie Policy
No Result
View All Result
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
  • About
  • Contact

Copyright 2025 © Smarter Shift Inc. and Energy Mix Productions Inc. All rights reserved.

Manage Cookie Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}
No Result
View All Result
  • Topics
    • Buildings & Infrastructure
    • Climate Equity & Justice
      • Energy Poverty
      • Indigenous Rights & Reconciliation
    • Climate Finance
      • Community Climate Finance
      • Finance & Investment
      • Insurance & Liability
      • Subsidies
    • Climate Impacts & Adaptation
      • Biodiversity & Habitat
      • Drought & Wildfires
      • Forests & Deforestation
      • Health & Safety
      • Heat & Temperature
      • Ice Loss & Sea Level Rise
      • Severe Storms & Flooding
    • Emissions
      • Carbon Levels & Measurement
      • CCS & Negative Emissions
      • Methane
    • Energy
      • Renewables
      • Fossil Fuels
      • Hydrogen
      • Nuclear
      • Batteries & Storage
      • Energy Efficiency
      • Power Grids
    • Food & Agriculture
    • Industry
      • Data Centres & Tech
      • Critical Minerals & Mining
      • Petrochemicals & Plastics
    • Policy & Politics
      • Carbon Pricing
      • COP Conferences
      • Elections
      • Energy Politics
      • International Security & War
      • Legal & Regulatory
    • Research & Innovation
      • International Agencies & Studies
      • Research & Development
    • Society & Culture
      • Climate Action
      • Mis/Disinformation & Greenwashing
      • Jobs & Training
      • Leisure & Recreation
      • Media, Messaging, & Public Opinion
    • Transportation & Mobility
      • Electric Vehicles
      • Shipping & Aviation
      • Transit
      • Walking, Biking & Micromobility
  • Regions
    • Africa
    • Arctic & Antarctica
    • Asia
    • Australia
    • Canada
    • International
    • Mexico & the Caribbean
    • Middle East
    • Oceans
    • Small Island States
    • South & Central America
    • Subnational
    • United States
    • UK & Europe
  • Special Coverage
    • The Weekender
    • IEA2026
    • Canada’s Major Projects Office
    • Hidden Wonder Valley
    • COP30
    • Cities & Communities
    • Heat & Power
    • Community Climate Finance
  • More Resources
  • About
  • Contact

Copyright 2025 © Smarter Shift Inc. and Energy Mix Productions Inc. All rights reserved.