The Quebec, Newfoundland and Labrador, and federal government have reached a tentative agreement for up to 14,000 megawatts of hydropower development and 2,000 MW of wind, in what Prime Minister Mark Carney described as the largest clean energy investment in North America.
The deal will include new and existing hydroelectric developments in Labrador, as well as hydropower and wind projects along the Churchill River, The Canadian Press reports.
“Today’s announcement will produce enough clean electricity to power every car, truck, motorcycle, and bus in Canada,” Carney said. “It will generate enough power to light, heat, and cool the homes in Toronto, Montreal, and Vancouver combined.”
It may also end decades of tension between Newfoundland and Labrador and Quebec, CP writes—if negotiators can hammer out final, binding agreements amid an election campaign in Quebec and the possible installation of a new provincial government.
“Canada is extending its unique advantage in clean, reliable, and affordable power,” Carney said in a release. “Because when we master energy, we master our destiny. Through cooperative federalism, we are unlocking our immense potential, building big, building sustainably, building in partnership, and building Canada strong for all.”
The announcement “promises to unlock an enormous amount of new reliable clean power and transmission to the benefit of people and businesses across Atlantic Canada, Quebec, and beyond,” agreed Canadian Climate Institute President Rick Smith. “This is the scale of clean energy ambition that is necessary across the country in order to meet the Prime Minister’s commitment to doubling the size of Canada’s electricity grids and electrifying more of the national economy. It demonstrates that positive outcomes can be achieved through co-operation between governments, including Indigenous communities, that drives investment and leads to more interconnected provincial electricity markets.”
“Today’s announcement is an example of what’s possible when provincial and federal governments come together to advance the nation-building project that underpins all others: the buildout of Canada’s clean, affordable, and reliable electricity system,” said Evan Pivnick, associate director of public affairs at Clean Energy Canada. “Coupled with infrastructure investments that will support the electrification of critical minerals mining, today’s announcement is a meaningful step towards positioning this country as a clean energy superpower.”
David Pickup, director of the Pembina Institute’s electricity program, said the deal would help build Canadian prosperity. “When energy resources are effectively shared across provinces, Canadians benefit through more affordable and resilient electricity systems, as well as the economic benefits such as local job creation and further investment.”
But Pickup warned that Ottawa is falling short on policies to electrify Canadian transportation, industry, and buildings, pointing to Friday’s announcement that completed the repeal of the federal sales mandate for electric vehicles.
Making Canada Less Dependent
The story led the evening news digest published in the United States by Pulitzer Prize-winning Inside Climate News.
“New U.S. tariffs on Canadian goods are set to take effect this week, underscoring Carney’s desire to make his country less dependent on an often-uncooperative neighbour,” wrote Inside Climate reporter Dan Gearino. And for U.S. utilities, “having the opportunity to buy renewable energy from Canada is significant, given how the Trump administration has undermined states’ ability to build their own renewable energy, including hostility toward offshore and onshore wind.”
Citing a media briefing ahead of the political announcement, CP says the framework agreement outlines plans for Hydro-Québec and Newfoundland and Labrador Hydro to divvy up power from the Churchill Falls generating station and launch new hydro, wind, and transmission projects worth more than $50 billion.
They did not provide reporters with a copy of the agreement.
The draft agreement proposes a new, 2,700-megawatt generating station at Gull Island on the Churchill River and upgrades to the existing 5,428-megawatt power plant at Churchill Falls, which is jointly owned and operated by provincial utilities.
It includes plans for transmission lines and feasibility studies for a second powerhouse at Churchill Falls and a 2,000-megawatt wind development in the Churchill River area, which could be partially owned by a private partner, officials said.
$49 Billion Over 50 Years
If finalized, the deal also would allow Newfoundland and Labrador to transmit up to 985 megawatts of power from Labrador through Quebec to markets in the United States.
The arrangement would earmark about 2,750 megawatts of power for Newfoundland and Labrador Hydro and 8,515 megawatts for Hydro-Québec, though the figures could increase if the partners proceed with the expansion of the Churchill Falls plant.
The expected return for Newfoundland and Labrador over the 50-year agreement is an estimated $49 billion, officials said.
Negotiators hope to hammer out a final deal by the end of this year. However, Quebec Premier Christine Fréchette must call a provincial election by Oct. 5 and it’s not clear how the campaign, nor the potential installation of a new government, could affect those goals.
Polls suggest Fréchette’s Coalition Avenir Québec government is not favoured to form the next government, trailing behind the sovereigntist Parti Québécois and the Liberals.
“I see the Parti Québécois is interested in tearing up this agreement. They don’t want to implement it,” Fréchette said. “So what do they offer to Quebecers if it’s not this agreement? Where will they find the 10,000 megawatts we are bringing to Quebec?”
“In the current geopolitical context, it is vital for every nation to secure its energy future,” Fréchette said in the PMO release. “Through this partnership, we are supporting the energy transition and enabling the growth of our economy through renewable energy, while ensuring our energy independence.”
On social media, PQ leader Paul St-Pierre Plamondon said it was not true he would automatically shred the proposal.
“The reality is that no one has read the agreement,” he wrote. “If the agreement is positive for Quebec, then obviously it will be in a Parti Québécois government’s interest to maintain it.”
Newfoundland and Labrador Premier Tony Wakeham said he had no control over the election outcome in Quebec, but trumpeted the non-binding agreement as a win for the two provinces and the federal government.
Turning Hydropower Into Revenue
Newfoundland and Labrador is eager to turn the river’s hydroelectric potential into revenue, and Quebec is looking to secure a reliable power supply for decades to come. Negotiations began several years ago, resulting in a previous framework agreement signed in 2024.
However, Wakeham sent a team back to the bargaining table after he and his Progressive Conservatives were elected last year. He was looking for more power, more value, and transmission rights through Quebec, he said at the time.
Wakeham kicked off his election campaign last fall promising to hold a public referendum on any final deals. He walked back that promise on Monday, saying a referendum would not happen.
“I know there will be people in our province who will be disappointed in that, but I accept that,” Wakeham said in an interview. “The time was now. There was an opportunity right now.”
The federal government will kick in $10 billion in financing for several proposed projects, including transmission lines and the Gull Island development, according to a news release.
Hydro-Québec would also pay more for power from the Churchill Falls plant, beginning at 1.8 cents per kilowatt hour in 2027, according to a graph provided to the media. That price would increase until 2077, averaging out to an effective price of 7.4 cents per kilowatt hour over the next 50 years.
The previous draft agreement signed in 2024 landed on an average effective price of 5.9 cents per kilowatt hour.
Hydro-Québec currently pays just 0.2 cents per kilowatt hour under a contract signed in 1969 which was set to expire in 2041.
Many in Newfoundland and Labrador have long viewed the current arrangement as unfair and even unjust, and the province has tried unsuccessfully to have the deal quashed in court. Monday’s tentative agreement would terminate the 1969 deal and end what Wakeham described as one of the worst chapters in Newfoundland and Labrador history.
“When we went into these negotiations, we made it clear there was one thing which we would not compromise: that Newfoundlanders and Labradorians must always be the primary beneficiaries of our own resources,” he told the crowd.
The main body of this report was first published by The Canadian Press on Aug. 17, 2026.
This is a corrected story. A previous version said the price Hydro-Québec would pay for power would increase until 2027, averaging out to an effective price of 7.4 cents per kilowatt hour over the next 50 years. In fact, the price Hydro-Québec would pay would increase until 2077, according to a graph that was provided to news outlets.












What about Muskrat Falls? What is the story?