A new map of data centres in Alberta shows proposed AI facilities demanding more than 100 times the electricity used by existing ones in the province, a spike that comes with significant emissions impact.
The Alberta Data Centre Watch website and map, built by Lacombe County resident Sarah Yurchevich in her spare time, pulls together information from publicly available sources and shows exponential differences between the few data centres currently operating and the dozens of new AI data centres proposed, approved, or under construction in the province.
For the most part, existing data centres use less than 10 megawatts (MW) of grid power each, in many cases much less. One exception is the Hut 8 cryptocurrency mining facility in Medicine Hat, which is backed by Eric Trump and Donald Trump Jr. and has access to up to 67 MW of power. The new breed of AI data centres proposed for Alberta would be much bigger, many up to 1,000 MW or 1 gigawatt (GW). Celebrity investor Kevin O’Leary has filed documents with the province seeking approval for up to 9 GW of power for the proposed Wonder Valley data centre south of Grande Prairie.
Yurchevich told The Energy Mix she decided to build her own website after becoming frustrated with her inability to find a single source of information about what was going on with data centres in the province. After working in information technology for the last 15 years, mostly on backend web development, it took her about six weeks to research and launch the data centre map.
Yurchevich’s map shows that demand for data centre power based on grid connection requests submitted to the Alberta Electric System Operator (AESO) is up 124% over last year’s average. Beacon Data Centre’s plan for six new locations in Alberta is equal to 44% of the entire province’s total average demand in 2025.
Almost half of these large data centres will “bring their own power,” building or using existing gas-powered plants. The Pembina Institute, a clean energy think tank, said in a statement July 8 that developers are “being forced to choose gas-fired generation, rather than a combination of technologies.”
David Pickup, director of Pembina’s electricity program, said Meta’s new Sturgeon Data Centre alone would use more electricity than the entire city of Calgary and emit three megatonnes of carbon dioxide, equivalent to 10% of Alberta’s total electricity sector emissions. It’s hard to know the total emissions for all data centres, as Alberta’s reporting on greenhouse gas emission reductions relies on federal data from 2024.
If Wonder Valley were fully built out as planned, it would emit 26 to 30 megatonnes of CO2 per year without mitigation measures like carbon capture, effectively erasing all the reductions the province achieved when it phased out coal power.
“What is really, really, really important to me on the website is to provide accurate, publicly available, first source information,” Yurchevich said. “Rather than an advocacy website, I thought it would be a stronger tool to have a site that is impartial.”
Yurchevich explained her sourcing policy: “official records are used to confirm facts while company materials show what a developer says or plans, not what has happened.”
She started with the Alberta Major Projects website, then by looking through municipal meeting minutes, the Alberta Utilities Commission website, and other provincial government sites, she got the bigger picture.
Alberta’s government website offers an online inventory of major projects but there’s no separate category for data centres and information is limited to location, cost, status, and timeline. Many of the fields for existing projects are incomplete.
Technology and Innovation Minister Nate Glubish did not respond to questions from The Mix about the lack of information on water and power requirements for data centre projects, reporting requirements for companies, or when to expect the new guidelines for data centre development promised at recent town hall meetings.
Glubish told reporters last month that he was aware of about 60 data centre proposals working their way through the government’s concierge service, but the government’s list includes only half that number.
All details in Yurchevich’s map are verified and labeled, including missing, conflicting, or unresolved information. News reports were used for context and research leads but rarely as primary sources of information.
The website tracks and reports information submitted to regulators, including power sources, emissions, cooling technology, water demand and source, wastewater, stormwater, chemicals, fuel storage, batteries, nearby receptors, mitigation, monitoring, and emergency response information.
“I wanted it to be as neutral as I physically could, so that someone couldn’t look at the site and dismiss it as politically leaning one way or the other,” she said, and “I’m trying my darndest to keep it that way.” After building a working model of the website using Astro, and with help from ChatGPT, she went through a couple of rounds of testing with friends.
“I don’t want it to be a big wall of text thrown at people because I hate looking at that,” she said. “It’s definitely been a lot of work breaking it down into chunks of the energy use, the water use, and what are the actual impacts as a constituent.”
Yurchevich reached out to the municipal offices of three communities with large data centres proposed— Olds, Sturgeon County, and the Municipal District of Greenview—to confirm her facts and ask for feedback. Only Greenview did not respond.
She also contacted Sturgeon Lake Cree Nation’s Chief Sheldon Sunshine for his input. The map includes the Treaty number where each data centre is located.
Then Yurchevich put the website through the most rigorous test of all: she had her mom take a look at it. The verdict from her was, ‘the website’s great, but what does this mean, what story is this supposed to be telling me?’”
After that, Yurchevich updated the home page to explain some of the terminology and measures, like the difference between a megawatt and a gigawatt. She also added graphics to illustrate how just one proposed data centre near Indus will need 480 times more power than an existing data centre in Edmonton.
She said she soon discovered “there’s a whole lot more going on out there than I realized.”
“What I want is people who are genuinely looking to research this, to be able to find the information instead of just hearing things on social media and not getting the full picture.”
Yurchevich is looking for help sharing the link to the data centre website on social media as she doesn’t have a big presence on those platforms. “The more people click on it, the more people share, the more people see it just the better it is, the more information people have,” she said.
Find the map on Instagram or contact Yurchevich via the website.













I am ” the mom” and I could not be more proud of my daughter. She has always cared for her country, especially Alberta. But it’s her love for our planet that has been paramount.
She is terrified at the speed in which people, most importantly big corporations and the ultra rich, are rapidly destroying our world for their own personal gain. She is doing what she can to make more people aware of what these data centers are truly about. Hopefully, it will help make more people aware of what is happening in our own back yard.
The world needs more people to actively get involved in our worlds current situation if any change for the better is ever going to happen.
Wow, mom, it’s an honour to hear from you and a joy to read your words.
(And in more than a dozen years running this site, that’s the first time I’ve had a chance to address someone as “mom”!!)
Sarah’s doing amazing work, and we’re so pleased to have a chance to amplify it.
I’m so glad you shared this with us. The website is phenomenal, and I’ll be sharing it widely. Sarah is an inspiration to us all!
Thank you for creating this website. One aspect that I would like to see addressed in more detail is the projected financial benefits to Alberta of having these large data centre projects located here. Other than the new 2% special levy on computer equipment applicable to certain grid-tied data centres, which the UCP already appears to be waffling on, it is not clear to what extent the operation of these data centres will generate profits that will be subject to Alberta corporate income tax. If a data centre is simply one asset owned and operated by a foreign corporation, then it will be the foreign corporation that earns any profits, and how will the portion of that foreign corporation’s profits that will be subject to tax in Alberta be determined? My concern is that the foreign corporation may be able to structure its financial affairs so as to ensure that little if any corporate income tax ends up being payable in Alberta, resulting in Albertans bearing all of the fallout of hosting the data centre while receiving few if any benefits.
It amazes me that there is not much mention of Global warming and Climate disasters with these AI Data Centers. Seems the issue went away when these projects showed up.
Oh, the issue hasn’t gone away, and the connections are there to be made…..