• About
    • Which Energy Mix is this?
  • Climate News Network Archive
  • Contact
The climate news that makes a difference.
No Result
View All Result
The Energy Mix
  • Canada
  • UK & Europe
  • Fossil Fuels
  • Ending Emissions
  • Community Climate Finance
  • Clean Electricity Grid
  • Cities & Communities
SUBSCRIBE
DONATE
  • Canada
  • UK & Europe
  • Fossil Fuels
  • Ending Emissions
  • Community Climate Finance
  • Clean Electricity Grid
  • Cities & Communities
SUBSCRIBE
DONATE
No Result
View All Result
The Energy Mix
No Result
View All Result
  • Canada
  • UK & Europe
  • Fossil Fuels
  • Ending Emissions
  • Community Climate Finance
  • Clean Electricity Grid
  • Cities & Communities
  FEATURED
Biden Approves $8B Oil Extraction Plan in Ecologically Sensitive Alaska March 14, 2023
U.S. Solar Developers Scramble after Silicon Valley Bank Collapse March 14, 2023
$30.9B Price Tag Makes Trans Mountain Pipeline a ‘Catastrophic Boondoggle’ March 14, 2023
UN Buys Tanker, But Funding Gap Could Scuttle Plan to Salvage Oil from ‘Floating Time Bomb’ March 9, 2023
Biden Cuts Fossil Subsidies, But Oil and Gas Still Lines Up for Billions March 9, 2023
Next
Prev

Quebec’s Hydropower Era Ends as Last Big Megaproject Nears Completion

January 3, 2022
Reading time: 5 minutes
Full Story: The Canadian Press @CdnPressNews
Primary Author: Morgan Lowrie @Lowrie219

Fenerty/Wikimedia Commons

Fenerty/Wikimedia Commons

1
SHARES
 

Quebec is close to completing what will likely be the last big hydroelectric dam it ever builds, bringing an end to a decades-long era when hydro development was often seen as synonymous with the province’s growing economic power and cultural pride.

Quebec’s hydro dams have long provided its residents cheap electricity and bragging rights in the race to reduce global carbon emissions, with Premier François Legault suggesting just 2½ years ago the province could become the “green battery of North America,” The Canadian Press reports.

  • Concise headlines. Original content. Timely news and views from a select group of opinion leaders. Special extras.
  • Everything you need, nothing you don’t.
  • The Weekender: The climate news you need.
Subscribe

But as the premier signs lucrative export deals with states such as Massachusetts and New York, the province’s utility has acknowledged that the La Romaine-4 hydroelectric project—scheduled to enter service next year—could be the last major dam project for the foreseeable future.

Hydro-Québec spokesperson Francis Labbé confirmed the utility doesn’t have other hydro projects on the horizon. He said such projects take at least a decade to plan and build, and they don’t come cheap—as Romaine’s C$7.3-billion price tag attests.

In the meantime, prices for other kinds of renewable energy—such as wind power—have fallen, making them more attractive options, CP writes.

“It may come to a point where we come to the conclusion that we need another hydroelectric project. But right now, considering the delays, considering the cost, considering that we have other options, we will not go in this direction,” Labbé said in a recent interview.

Quebec started building the four-part La Romaine project—described at the time as the biggest construction project in Canada—in 2009. The commissioning of La Romaine-4, the last of the dams, was pushed back to 2022 from 2020 after a series of delays, including the pandemic and other health and safety concerns.

Labbé said the dam and reservoir are complete and work is under way on the power station. When it is commissioned next fall, it should supply about eight terawatt-hours of electricity per year, enough to power about 450,000 homes.

While Labbé says the utility has enough power in reserve to serve the province and its export contracts until 2025 or 2026, it will be putting out a call for tenders for projects to provide 300 megawatts of wind power and 480 megawatts of renewables, which could include wind and solar.

That’s in addition to the Apuiat wind energy project developed with the Innu of the Côte-Nord region, which should provide some 200 megawatts when it’s commissioned in 2024.

François Bouffard, an associate professor of electrical engineering at McGill University, says the megaprojects that propelled the provincial utility to early success are “a development model of the past.”

“If you look at the projects from the 1960s to the end of 1990s, if they were to redo this, it would never happen the way it did,” he told CP. “The environmental assessments would be a lot more robust, more complicated. We wouldn’t be able to trample Aboriginal rights like they have.”

Bouffard says the early dams relied on flooding large tracts of land, without regard for the Indigenous inhabitants of the area and without bothering to remove the vegetation underneath, which led to mercury contamination in fish.

While he said the La Romaine project has corrected some of those early mistakes by logging the area before the reservoir was created, he noted that Hydro-Québec still encounters opposition when it tries to build transmission lines through wilderness—something that came up when Maine residents voted against allowing lines to pass through their state in a referendum this fall.

“Nothing is really carbon-free,” he said.

In the absence of future hydropower projects, Hydro-Québec has been moving into other domains. In addition to wind partnerships, the company recently inaugurated its first two solar energy plants. It has also formed a subsidiary to help customers improve their energy efficiency, and it is working on large-scale batteries that can store surplus energy.

Experts say that far from becoming redundant, Quebec’s massive hydro dams will become more important than ever as the province shifts to alternative sources of power.

Louis Beaumier, executive director of the Trottier Energy Institute at Polytechnique Montréal, agreed that building more “titanic” dam projects doesn’t make sense, largely due to the cost.

But he said the main advantage of hydropower is that, unlike wind or solar, it provides a consistent stream of power that can be increased or decreased fairly easily to meet fluctuating demand. The power stored in the province’s reservoirs amounts to “the biggest battery you can every build,” he said, and one that puts Quebec in a uniquely advantageous position of being able to move forward with new technologies while always having hydro as a backup.

Bouffard and Beaumier agreed that the Crown corporation will have to adjust to yet more changes in the coming years. With the Quebec government as its only shareholder, Hydro-Québec’s mandate is to bring in revenue for the province, meet provincial electricity needs, and keep rates low—all at once.

Increasingly, the province has looked to expand sales to the United States in order to grow. Legault has made no secret of his desire to see the province expand exports to the northeastern United States, even as the province was dealt a blow when Maine voters rejected a plan to run transmission lines through their state to Massachusetts. (Legault has said he remains confident the project will go ahead).

Bouffard believes the future of the company may lie outside North America altogether, as it looks to sell its valuable expertise to developing countries. Beaumier, for his part, said the company should also play a role domestically as the federal government moves toward its goal of reaching net-zero emissions by 2050. He said Hydro-Québec could be doing more to help meet those goals.

Hydro-Québec’s Labbé underplayed the extent of the culture shift that is under way at the utility. While La Romaine is the last major project planned, he told CP, the company still has plenty of work to do managing and maintaining its 62 existing power stations, including plans already under way to make several of them more efficient.

“This is far from the end of hydroelectricity in Quebec,” Labbé said.

This report by The Canadian Press was first published December 21, 2021.



in Batteries / Storage, Canada, Clean Electricity Grid, Demand & Efficiency, Ending Emissions, Energy / Carbon Pricing & Economics, First Peoples, Hydropower, Solar, Sub-National Governments, Wind

The latest climate news and analysis, direct to your inbox

Subscribe

Related Posts

U.S. Bureau of Land Management/flickr
Oil & Gas

Biden Approves $8B Oil Extraction Plan in Ecologically Sensitive Alaska

March 14, 2023
67
David Dodge, Green Energy Futures/flickr
Community Climate Finance

U.S. Solar Developers Scramble after Silicon Valley Bank Collapse

March 14, 2023
97
EcoAnalytics
Media, Messaging, & Public Opinion

Canadians Want Strong Emissions Cap Regulations, Not More Missed Targets

March 14, 2023
72

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

I agree to the Terms & Conditions and Privacy Policy.

Trending Stories

Behrat/Wikimedia Commons

Hawaii Firm Turns Home Water Heaters into Grid Batteries

March 14, 2023
298
U.S. National Transportation Safety Board/flickr

$30.9B Price Tag Makes Trans Mountain Pipeline a ‘Catastrophic Boondoggle’

March 14, 2023
141
David Dodge, Green Energy Futures/flickr

U.S. Solar Developers Scramble after Silicon Valley Bank Collapse

March 14, 2023
97
Rebecca Bollwitt/flickr

Fossils Stay ‘Oily’, Gibsons Sues Big Oil, U.S. Clean Energy Booms, EU Pushes Fossil Phaseout, and Fukushima Disaster was ‘No Accident’

March 14, 2023
74
EcoAnalytics

Canadians Want Strong Emissions Cap Regulations, Not More Missed Targets

March 14, 2023
72
U.S. Bureau of Land Management/flickr

Biden Approves $8B Oil Extraction Plan in Ecologically Sensitive Alaska

March 14, 2023
67

Recent Posts

Raysonho/wikimedia commons

Purolator Pledges $1B to Electrify Last-Mile Delivery

March 14, 2023
50
United Nations

UN Buys Tanker, But Funding Gap Could Scuttle Plan to Salvage Oil from ‘Floating Time Bomb’

March 10, 2023
89
Gage Skidmore/Wikimedia Commons

Biden Cuts Fossil Subsidies, But Oil and Gas Still Lines Up for Billions

March 10, 2023
172
jasonwoodhead23/flickr

First Nation Scorches Imperial Oil, Alberta Regulator Over Toxic Leak

March 8, 2023
364
MarcusObal/wikimedia commons

No Climate Risk Targets for Banks, New Guides for Green Finance as 2 Federal Agencies Issue New Rules

March 8, 2023
234
FMSC/Flickr

Millions Face Food Insecurity as Horn of Africa Braces for Worst Drought Ever

March 8, 2023
241
Next Post
ExxonMobil/Wikimedia Commons

Exxon Following Blockbuster Video to Oblivion, Investment Exec Warns

The Energy Mix - The climate news you need

Copyright 2023 © Energy Mix Productions Inc. All rights reserved.

  • About
  • Contact
  • Privacy Policy and Copyright
  • Cookie Policy

Proudly partnering with…

scf_withtagline
No Result
View All Result
  • Canada
  • UK & Europe
  • Fossil Fuels
  • Ending Emissions
  • Community Climate Finance
  • Clean Electricity Grid
  • Cities & Communities

Copyright 2022 © Smarter Shift Inc. and Energy Mix Productions Inc. All rights reserved.

Manage Cookie Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
Manage options Manage services Manage vendors Read more about these purposes
View preferences
{title} {title} {title}