• About
    • Which Energy Mix is this?
  • Climate News Network Archive
  • Contact
Celebrating our 1,000th edition. The climate news you need
No Result
View All Result
The Energy Mix
  • Canada
  • UK & Europe
  • Fossil Fuels
  • Ending Emissions
  • Community Climate Finance
  • Clean Electricity Grid
  • Cities & Communities
SUBSCRIBE
DONATE
  • Canada
  • UK & Europe
  • Fossil Fuels
  • Ending Emissions
  • Community Climate Finance
  • Clean Electricity Grid
  • Cities & Communities
SUBSCRIBE
DONATE
No Result
View All Result
The Energy Mix
No Result
View All Result
  FEATURED
Soaring Fertilizer Prices Could Deliver ‘Silver Lining’ For Emissions, But Farmers Struggle to Limit Use June 26, 2022
BREAKING: UN Nature Summit, the ‘Paris Conference for Biodiversity’, Moves to Montreal in December June 19, 2022
‘LET’S SUE BIG OIL’: Legal Team Launches Class Action Campaign for B.C. Municipalities June 17, 2022
‘It Could Have Been Any of Us’, Colleague Says, After Brazil Confirms Murders of Bruno Pereira, Dom Phillips June 17, 2022
Infrastructure Gap a ‘Life and Death’ Matter as Northern Canada Warms June 17, 2022
Next
Prev
Home Climate & Society First Peoples

Dakota Access Pipeline Continues Accepting Oil After U.S. Judge Orders Shutdown

July 12, 2020
Reading time: 5 minutes
Primary Author: Compiled by Mitchell Beer @mitchellbeer

Joe Brusky/Flickr

Joe Brusky/Flickr

110
SHARES
 

The company behind the intensely controversial Dakota Access Pipeline isn’t explicitly defying a court order. But nor was it reported to have taken any steps last week to comply with Judge James Boasberg’s ruling that the line must shut down within 30 days, after failing to meet environmental assessment requirements.

Dallas-based Energy Transfer Partners “continued to fill [DAPL] with North Dakota crude oil on Wednesday and said it has no immediate plans to shut down the line, despite a federal judge’s order that it be stopped within 30 days for additional environmental review,” The Associated Press reported Wednesday. The company was still taking orders for shipments beyond Boasberg’s August 5 closure deadline.

“We are not shutting in the line,” spokesperson Vicki Granado told Bloomberg, adding that “we believe [the judge] exceeded his authority and does not have the jurisdiction to shut down the pipeline or stop the flow of crude oil.” 

The company later clarified it did not plan to defy Boasberg’s order, but said it would need 86 to 101 days to empty the pipeline and keep it in condition for future use. That estimate was part of an unsuccessful bid last week to persuade the judge to rescind his ruling. 

“The company says the line must be filled with an inert gas, such as nitrogen, to keep the pipe from corroding if oil no longer flows through it,” the Bismarck Tribune reports. “Energy Transfer outlined the process in a motion filed Wednesday evening in which it asked the judge to put the order on hold while it appeals the decision to a higher court.”

Citing the company, the Tribune says shutting down the pipeline will involve “a number of expensive” steps, including US$24 million to empty and preserve it and another $67.5 million for each year it stays out of service. “Energy Transfer also discloses the revenue hit it anticipates during a shutdown, estimating it will lose out on at least $2.8 million every day the line sits idle,” the local paper says.

“The severe economic toll—just as our nation is regaining its footing and struggling to emerge from a global pandemic—would be in the billions of dollars, with many thousands forced out of work,” the company’s court filing stated.

While he acknowledged costs associated with the shutdown, Earthjustice lawyer Jan Hasselman, attorney for the Standing Rock Sioux Tribe, said the company “has a history of wild exaggeration,” and in this case, “we think the claims are overblown”.

On Thursday, Boasberg said the company had “emphasized its understandable desire to be heard in the Court of Appeals as soon as possible,” and had meanwhile agreed to negotiate the logistics of a shutdown.

But by then, “Energy Transfer’s statement that DAPL was not being shut down caused a stir, with some observers asking whether the company intended to openly defy the federal court,” DeSmog says.

“To be clear, we have never suggested that we would defy a court order,” the company wrote. “Rather, DAPL is seeking appropriate relief from that order through the established legal process.”

On that basis, company spokesperson Lisa Coleman said investors “should not be concerned about the possibility of court sanctions against the company or its management,” DeSmog adds.

Hasselman said his client isn’t “overly worried” about how long it’ll take to shut the line down, after four years of fighting it in court. “If it takes longer than 30 days to drain the pipeline of oil, I don’t think that’s a major issue,” he told the Tribune. 

But Energy Transfer “is playing a very dangerous game,” he said, in an interview with Bloomberg. “They don’t get to ignore a federal court order just because they disagree with it.”

“Perhaps they’re taking their inspiration from the father of the Trail of Tears, Andrew Jackson. In response to the 1832 Supreme Court decision that established tribal sovereignty in the U.S.—Worcester vs. Georgia—President Jackson declared: ‘[Chief Justice] John Marshall has made his decision. Now let him enforce it,’” added the Bismarck, ND-based Lakota People’s Law Project. “But this is not 1832,” and “we will not let this corporation, this pipeline, or this president trample on our sovereignty.”

Energy Transfer’s bare-knuckle response to the court ruling is a vintage performance for its owner, billionaire pipeline mogul Kelcy Warren, who has apparently said he’s “proud of the Dakota Access oil project like it were his son,” Bloomberg reports.

The company’s refusal to begin the shutdown procedure “was, to Warren’s enemies in the Indigenous community and conservation circles, an incendiary statement that would only add to the bitterness remaining four years after the project stoked weeks of protests at the Standing Rock reservation in North Dakota,” the news agency writes. “To his supporters, it was classic Warren: The 64-year-old CEO, a fundraiser for…Donald Trump, has adopted a relentlessly aggressive approach to building pipelines.”

“Energy Transfer has taken the view that if you want to get anything built or done in this current regulatory environment, you have to be aggressive,” Hinds Howard, a portfolio manager at CBRE Clarion Securities LLC, told Bloomberg. “It’s a strategy and a corporate culture that’s maybe out of step with the times.”

In an editorial published Thursday, the Bismarck Tribune say any criticism resulting from Boasberg’s ruling should be directed not at the judge, but at the U.S. Army Corps of Engineers, for failing to conduct a proper environmental assessment before the pipeline was built.

“The more thorough environmental review known as an environmental impact statement is what the Standing Rock Sioux and other tribes have been asking for all along,” the editors write. “It’s what the Corps should have done in the first place before it granted the controversial easement allowing the pipeline to be built under Lake Oahe, just north of the Standing Rock Reservation.”

In his ruling last week, Boasberg opined that “when it comes to [the U.S. National Environmental Protection Act], it is better to ask for permission than forgiveness: if you can build it first and consider environmental consequences later, NEPA’s action-forcing loses its bite.”

Against that reality, “the Corps has repeatedly failed in its review of the pipeline, taking shortcuts that will now have serious ramifications for the state three years after the pipeline began operating,” the Tribune adds. “One example of failure is the agency’s environmental justice analysis, which is required under NEPA to determine whether low-income or minority communities would be disproportionately harmed by the project.”

But ultimately, that criticism lands on the former reality TV star and failed real estate magnate currently occupying the White House. “The Corps was prepared to do a full EIS,” the Tribune said, “until…Donald Trump pushed the project forward days after taking office in January 2017.”

In his ruling, Boasberg said a full EIS normally takes more than three years to complete. The Army Corps expected to finish its DAPL analysis in 13 months.



in First Peoples, Health & Safety, Legal & Regulatory, Pipelines / Rail Transport, Sub-National Governments, United States

The latest climate news and analysis, direct to your inbox

Subscribe

Related Posts

David/flickr
United States

U.S. Supreme Court Expected to Gut Emission Controls as Climate Scientists Petition for Plan B

June 26, 2022
580
pxhere
Environmental Justice

Environmental Racism Bill Passes Second Reading in House of Commons

June 26, 2022
79
Graco/Facebook
Food Security

Soaring Fertilizer Prices Could Deliver ‘Silver Lining’ For Emissions, But Farmers Struggle to Limit Use

June 27, 2022
116

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

I agree to the Terms & Conditions and Privacy Policy.

Trending Stories

David/flickr

U.S. Supreme Court Expected to Gut Emission Controls as Climate Scientists Petition for Plan B

June 26, 2022
580
Graco/Facebook

Soaring Fertilizer Prices Could Deliver ‘Silver Lining’ For Emissions, But Farmers Struggle to Limit Use

June 27, 2022
116
Konrad Summers/Kern West Oil Museum via Wikimedia Commons

Imperial Oil Backs Lithium Recovery Project in Alberta’s Leduc Oilfield

June 26, 2022
97
pxhere

Environmental Racism Bill Passes Second Reading in House of Commons

June 26, 2022
79
stockvault

Animal Agriculture Could Reduce Future Pandemic Risk, UK Researchers Say

June 26, 2022
73
Gustavo Petro Urrego/flickr

Colombia’s President-Elect Has ‘Ambitious’ Plans to Halt Amazon Deforestation

June 26, 2022
67

Recent Posts

Adam E. Moreira/wikimedia commons

Suspend Transit Fares, Not Gas Tax, Climate Advocates Urge Biden

June 26, 2022
55
moerschy / Pixabay

Pandemic Drives Up Support for Climate Action, Pessimism About Elected Leaders

June 26, 2022
27
hellomike/flickr

No Public Input as Canada Finalizes Climate Plan for Airlines

June 27, 2022
37
Heinrich-Böll-Stiftung Southeast Asia/wikimedia commons

Japan, Korea Sell Vietnam on Gas Amid Crackdown on Climate Activists

June 26, 2022
22
https://en.wikipedia.org/wiki/Wikipedia:Featured_picture_candidates/Barrow_Offshore_Wind_Farm

Global Offshore Wind Pipeline Doubles to 846 Gigawatts

June 26, 2022
38
TAFE SA TONSLEY/Flickr

U.S. Renewables Industries Scramble to Reuse, Recycle Before Waste Volumes Skyrocket

June 26, 2022
63
Next Post
Where waste often ends up – a disposal site at Agbogbloshie in Ghana. Image: By Fairphone

World wilts beneath weight of e-waste and plastic

The Energy Mix

Copyright 2022 © Smarter Shift Inc. and Energy Mix Productions Inc. All rights reserved.

Navigate Site

  • About
  • Contact
  • Privacy Policy and Copyright
  • Cookie Policy

Follow Us

No Result
View All Result
  • Canada
  • UK & Europe
  • Fossil Fuels
  • Ending Emissions
  • Community Climate Finance
  • Clean Electricity Grid
  • Cities & Communities

Copyright 2022 © Smarter Shift Inc. and Energy Mix Productions Inc. All rights reserved.

Manage Cookie Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
Manage options Manage services Manage vendors Read more about these purposes
View preferences
{title} {title} {title}